The Speaker Connolly Tavern, Firhouse Road, Dublin 24, D24E400.
Data updated 12 Sept 2026 · register lag up to 7 days · sources & freshness
SD24A/0228W is a planning application for permission at The Speaker Connolly Tavern, Firhouse Road, Dublin 24, D24E400., received by South Dublin County Council on 16 Oct 2024 and first seen by Planning Register on 11 Sept 2026. The application describes: Seabren Developments Limited intend to apply to South Dublin County Council for planning permission at the Speaker Connolly Tavern. The site is bounded by Firhouse Road to the northwest, Ballycullen Avenue to the northeast, Firhouse Shopping Centre and car park to the south and neighbourhood shops to the east of the site. Vehicular access to the site will be from the existing vehicular access on Ballycullen Avenue with the existing right of way to and from the Supervalu Shopping Centre maintained. The proposed development will consist of the demolition of the Speaker Connolly public house including the part single part two storey public house, and ancillary stores and structures (c.411sqm), on a development site of 0.323 Hectares (overall site area 0.332 Ha), and the development of 55 residential units together with commercial uses (gross floor area 7351.4 sq.m.) all in one building ranging in height from 4 to 6 storeys and part basement, comprising: • 17 One Bed Apartments • 38 Two Bed Apartments • 1 no. Public House and Restaurant (c.457.9 sq.m), 1 no. Cafe (c. 72 sq.m) and 1 no. Beauty Salon 27sq.m at ground floor level • 1 no. Medical Centre 144Sq.m and 1 no. Gym 114.8 sq.m at first floor level • Existing basement will be used as a plant room (c.127.6 sq.m). The works include removal of the boundary wall along Ballycullen Avenue, reconfiguration of the existing entrance, access road and public footpath and use of the existing internal access road including the vehicular link between Ballycullen Avenue and the Firhouse Shopping Centre. The development will also consist of the provision of enhanced pedestrian infrastructure, provision of communal open space (c.297 sq.m) at podium level and related play areas, public open space (c.390 )including hard and soft landscaping, boundary treatment, street furniture, car parking along the internal access road (2 visitor spaces), below podium car parking (25 no. spaces, including 2 accessible spaces and 2 car share spaces), electric vehicle charging points (4. no. of spaces ), bicycle parking (104 long stay, 48 short stay spaces and 4 cargo bike spaces), ESB substation and electrical services area, piped infrastructural services and connections to existing public services, ducting; plant, waste management provision, SuDS measures including Green/Blue roofs, stormwater management, signage; public lighting, solar panels as well as telecommunications infrastructure including 18 No. antennas enclosed in 9 No. shrouds and 6 No. transmission dishes, together with all associated equipment and all ancillary site development and excavation works above and below ground. An Coimisiún Pleanála-322215-25 Condition 10:. The council granted permission on 10 Mar 2025. The five-week observation window closed on 20 Nov 2024. An Coimisiún Pleanála decided appeal 322215 on 11 Aug 2025 (grant conditions). The site is zoned M3 — neighbourhood centre under the South Dublin County Council development plan. Within 500 m there are 60 other decided applications in the last five years and 3 appeals.
Proposal
Seabren Developments Limited intend to apply to South Dublin County Council for planning permission at the Speaker Connolly Tavern. The site is bounded by Firhouse Road to the northwest, Ballycullen Avenue to the northeast, Firhouse Shopping Centre and car park to the south and neighbourhood shops to the east of the site. Vehicular access to the site will be from the existing vehicular access on Ballycullen Avenue with the existing right of way to and from the Supervalu Shopping Centre maintained. The proposed development will consist of the demolition of the Speaker Connolly public house including the part single part two storey public house, and ancillary stores and structures (c.411sqm), on a development site of 0.323 Hectares (overall site area 0.332 Ha), and the development of 55 residential units together with commercial uses (gross floor area 7351.4 sq.m.) all in one building ranging in height from 4 to 6 storeys and part basement, comprising: • 17 One Bed Apartments • 38 Two Bed Apartments • 1 no. Public House and Restaurant (c.457.9 sq.m), 1 no. Cafe (c. 72 sq.m) and 1 no. Beauty Salon 27sq.m at ground floor level • 1 no. Medical Centre 144Sq.m and 1 no. Gym 114.8 sq.m at first floor level • Existing basement will be used as a plant room (c.127.6 sq.m). The works include removal of the boundary wall along Ballycullen Avenue, reconfiguration of the existing entrance, access road and public footpath and use of the existing internal access road including the vehicular link between Ballycullen Avenue and the Firhouse Shopping Centre. The development will also consist of the provision of enhanced pedestrian infrastructure, provision of communal open space (c.297 sq.m) at podium level and related play areas, public open space (c.390 )including hard and soft landscaping, boundary treatment, street furniture, car parking along the internal access road (2 visitor spaces), below podium car parking (25 no. spaces, including 2 accessible spaces and 2 car share spaces), electric vehicle charging points (4. no. of spaces ), bicycle parking (104 long stay, 48 short stay spaces and 4 cargo bike spaces), ESB substation and electrical services area, piped infrastructural services and connections to existing public services, ducting; plant, waste management provision, SuDS measures including Green/Blue roofs, stormwater management, signage; public lighting, solar panels as well as telecommunications infrastructure including 18 No. antennas enclosed in 9 No. shrouds and 6 No. transmission dishes, together with all associated equipment and all ancillary site development and excavation works above and below ground. An Coimisiún Pleanála-322215-25 Condition 10:
- Status
- Appeal decided
- Decision
- Grant permission on 10 Mar 2025
- Floor area
- 7,351 m²
- Site (from polygon)
- 3,679 m²
- Location precision
- site (coords_polygon)
Timeline
- 16 Oct 2024New applicationObservation window closed 20 Nov 2024
- 10 Dec 2024Further information requested
- 12 Feb 2025Further information received
- 10 Mar 2025DecisionAppeal window closed 7 Apr 2025
- 7 Apr 2025Appeal lodged

Full planning report for 53.28186, -6.34102
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Commencement
No commencement notice matched to this reference.
Zoning at the site
DC: To protect, improve and provide for the future development of District Centres
A local centre: shops, services and apartments over them, serving the surrounding housing.
Designations within 250 m
OPW flood extent nearby — flag only (licence); floodinfo.ie.
- Natural Heritage Area (incl. proposed) · 1
- Radon risk area · 2
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 115157). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: https://planning.agileapplications.ie/southdublin/application-details/69829.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |