Approved in Jul 2024. Building started in 2025.

  1. 19 Mar 2024Received
  2. 1 Jul 2024Approved
  3. 12 Jul 2024Final approval
  4. 13 Jan 2025Building started
Status
Building startedi
Decision
Approved · 1 Jul 2024
Council
South Dublin County Council
Type
Permission
Site
307 m²

What’s proposed

Construction of a first floor side extension with a flat roof profile over the existing ground floor structure, an extended ground floor rear extension, internal ground and first floor modifications, 1 no. new window to both side elevations, plus al associated site works

Planning details

Reference
SD24B/0112
Local authority
South Dublin County Council
Status
Commenced · register status “Final Grant”
Received
19 Mar 2024
Decision due
2 Jul 2024 · decided 1 Jul 2024
Decision
Grant permission on 1 Jul 2024
Site area
307 m² from the mapped boundary, not the council's figure

Live near 5 Weston Crescent?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 2 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Building started

  • 13 Jan 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0124449SD

Zoning

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

Flood area nearby (OPW maps). floodinfo.ie ↗

Where this comes from

National planning feed (NPAD), fetched 14 Oct 2026, 01:45.

Source: National Planning Application Database · fetched 14 Oct 2026, 01:45
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.014 Oct 2026, 01:45open
Summary

SD24B/0112 is a planning application to South Dublin County Council for construction of a first floor side extension with a flat roof profile over the existing, received on 19 Mar 2024; permission was granted on 1 Jul 2024.