0.564ha site at Site D, Liffey Valley Office Campus, Dublin 22
Data updated 12 Sept 2026 · register lag up to 7 days · sources & freshness
SD25A/0297W is a planning application for permission at 0.564ha site at Site D, Liffey Valley Office Campus, Dublin 22, received by South Dublin County Council on 10 Mar 2026 and first seen by Planning Register on 11 Sept 2026. The application describes: The construction of a partially two storey over basement motor sales and service building, max. height of c. 11.6 metres with a total gross above ground level floor area of c. 2,198sq m. The development will include on-grade car and bicycle parking spaces, with vehicle display spaces on-grade and at basement level. The proposal also includes the reuse of the existing vehicular access to the north of the site, ramped access to basement level, all associated site enabling and excavation works, boundary treatments, hard and soft landscaping, together with building mounted signage, site signage and flagpoles. The council granted permission on 7 Apr 2026. The five-week observation window closed on 14 Apr 2026. The site is zoned C1.1 — retail warehousing under the South Dublin County Council development plan. Within 500 m there are 44 other decided applications in the last five years.
Proposal
The construction of a partially two storey over basement motor sales and service building, max. height of c. 11.6 metres with a total gross above ground level floor area of c. 2,198sq m. The development will include on-grade car and bicycle parking spaces, with vehicle display spaces on-grade and at basement level. The proposal also includes the reuse of the existing vehicular access to the north of the site, ramped access to basement level, all associated site enabling and excavation works, boundary treatments, hard and soft landscaping, together with building mounted signage, site signage and flagpoles.
- Status
- Final Grant
- Decision
- Grant permission on 7 Apr 2026
- Final grant
- 19 May 2026
- Permission expires
- 18 May 2031
- Floor area
- 4,163 m²
- Site (from polygon)
- 5,740 m²
- Location precision
- site (coords_polygon)
Timeline
- 30 Jan 2026Further information requested
- 10 Mar 2026Further information received
- 10 Mar 2026New applicationObservation window closed 14 Apr 2026
- 7 Apr 2026DecisionAppeal window closed 5 May 2026

Full planning report for 53.35439, -6.39531
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
MRC: To protect, improve and provide for the future development of a Major Retail Centre
Zoned for bulky-goods retail warehousing — large sheds, large car parks.
Designations within 250 m
No OPW flood extent nearby.
- NIAH-recorded building · 8
- Radon risk area · 3
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 116037). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: https://planning.agileapplications.ie/southdublin/application-details/69442.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|