PlanningRegister.ie
South Dublin County Council · SDZ22A/0011

Thomas Omer Way

Approved in Feb 2023. Built and signed off.

This is Thomas Omer Way, by Department of Education. Read the scheme page →

  1. 2 Aug 2022Received
  2. 16 Feb 2023Approved
  3. 14 Aug 2023Building started
  4. 8 Apr 2025Signed off
Status
Building started
Decision
Approved · 16 Feb 2023
Council
South Dublin County Council
Type
SDZ Application
Site
1.94 ha

What’s proposed

The proposed primary school will extend to c3,355sq.m will be 2 storeys in height and will comprise 16 no. classrooms with an additional 2 classroom Special Educational Needs Unit; a General Purpose Hall and all ancillary teacher and pupil amenities and facilities. The proposed development also provides for hard and soft play areas, including 2 no. outdoor ball courts, bicycle parking, staff car parking, vehicle drop off and set down areas. Photovoltaic Panels (PV) are proposed on roofs in addition to EV Charging Points and a packaged Biomass heating plant. The proposed development also provides for all landscaping and boundary treatments and all associated site development works. Access to the site will be via a new junction and access road off Thomas Omer Way. The new access road will run south off Thomas Omer Way and then west into the site. The proposed access road Is in accordance with the Clonburris Strategic Development Zone (SDZ) Planning Scheme and incorporates public lighting, footpaths and cycle tracks. A further pedestrian / cycle only connection to Thomas Omer Way ls also proposed along the western green corridor, west of the proposed school building

Planning details

Reference
SDZ22A/0011
Local authority
South Dublin County Council
Status
Commenced · register status “Final Grant”
Received
2 Aug 2022
Decision due
17 Feb 2023 · decided 16 Feb 2023
Decision
Grant permission on 16 Feb 2023
Site area
1.94 ha from the mapped boundary, not the council's figure

Live near Thomas Omer Way?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 2 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Building started

  • 14 Aug 2023 · Builder told the council work was starting CN0104034SD

Zoning

R3 — Rural cluster

A small rural settlement where only modest infill serving local need is envisaged.

Where this comes from

National planning feed (NPAD), fetched 14 Oct 2026, 01:45.

Source: National Planning Application Database · fetched 14 Oct 2026, 01:45
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.014 Oct 2026, 01:45open
Summary

SDZ22A/0011 is a planning application to South Dublin County Council for the proposed primary school will extend to c3,355sq.m will be 2 storeys in height and, received on 2 Aug 2022; permission was granted on 16 Feb 2023.