Black Lough , Tawnamore , Co. Sligo
- 14 Mar 2017Received
- 3 May 2017Conditional
- 3 Jun 2017Final grant
- 2 Jun 2022Permission expires
- Status
- Granted with conditions
- Decision
- Conditional · 3 May 2017
- Council
- Sligo County Council
- Type
- PERMISSION
- Site
- 19.16 ha
What’s proposed
a ten year permission for development consisting of: (a) erection of four wind turbines with blade tip height of 124.33m (78.33m hub height, 92m rotor diameter) (b) cranage and assembly hardstand areas adjacent to each turbine (c) control room and parking spaces (d) cabling between each turbine (e) widening of existing access road and provision of new sections of access road to serve wind turbines (f) stilling ponds (g) peat reinstatement areas (h) replacement bridge across Gowlan River and realignment of approaches to the bridge (i) use of existing borrow pit and (j) all associated ancillary infrastructure. An Environmental Impact Statement (EIS) and a Natura Impact Statement (NIS) have been submitted with the application. The proposed development is located
1793 is a planning application to Sligo County Council for a ten year permission for development consisting of: (a) erection of four wind turbines, received on 14 Mar 2017; permission was granted with conditions on 3 May 2017.
Planning details
- Reference
- 1793
- Local authority
- Sligo County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 14 Mar 2017
- Observations close
- 18 Apr 2017 (closed 3440 days ago)
- Decision due
- 8 May 2017 · decided 3 May 2017
- Decision
- Conditional on 3 May 2017
- Proposed development
- a ten year permission for development consisting of: (a) erection of four wind turbines with blade tip height of 124.33m (78.33m hub height, 92m rotor diameter) (b) cranage and assembly hardstand areas adjacent to each turbine (c) control room and parking spaces (d) cabling between each turbine (e) widening of existing access road and provision of new sections of access road to serve wind turbines (f) stilling ponds (g) peat reinstatement areas (h) replacement bridge across Gowlan River and realignment of approaches to the bridge (i) use of existing borrow pit and (j) all associated ancillary infrastructure. An Environmental Impact Statement (EIS) and a Natura Impact Statement (NIS) have been submitted with the application. The proposed development is locatedAs published by the register.
- Site area
- 19.16 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Full planning report for 54.17727, -8.93340
Zoning, appeals, sold prices, flood and heritage — the whole area in one PDF.
No account, no payment. Not a statutory planning search.
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
No other designation nearby.
Provenance
Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 459548). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/SligoCC/AppFileRefDetails/1793/0.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|