Approved in May 2023. Building started in 2024.

  1. 24 Feb 2023Received
  2. 17 Apr 2023Conditional
  3. 29 May 2023Final approval
  4. 28 May 2024Building started
Status
Building startedi
Decision
Conditional · 17 Apr 2023
Council
Sligo County Council
Type
PERMISSION
Site
1,305 m²

What’s proposed

development consisting of (i) 336m2 of roof mounted photovoltaic panels, (ii) the erection of a roof mounted heat pump and (iii) the installation of a revolving door and accessible entrance door at the front entrance, together with all associated site works and services

Planning details

Reference
2360033
Local authority
Sligo County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
24 Feb 2023
Decision due
20 Apr 2023 · decided 17 Apr 2023
Decision
Conditional on 17 Apr 2023
Site area
1,305 m² from the mapped boundary, not the council's figure

Live near Block G?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 2 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 28 May 2024 · Builder told the council work was starting CN0115682SO

Zoning

S3 — Community infrastructure

Reserved for civic, religious, community, education, health-care and social infrastructure.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2360033 is a planning application to Sligo County Council for development consisting of (i) 336m2 of roof mounted photovoltaic panels, (ii) the, received on 24 Feb 2023; permission was granted with conditions on 17 Apr 2023.