PlanningRegister.ie
Sligo County Council · 2360254

Main Street, Ballisodare, Sligo

Approved in Dec 2023. Building started in 2024.

  1. 20 Sept 2023Received
  2. 14 Nov 2023Conditional
  3. 18 Dec 2023Final approval
  4. 30 Apr 2024Building started
Status
Building startedi
Decision
Conditional · 14 Nov 2023
Council
Sligo County Council
Type
PERMISSION
Units
1
Site
337 m²

What’s proposed

to construct a block of two semi-detached, 2.5 storey, 3-bedroom houses including private open space, site landscaping, provision of vehicular access and all associated site works and service connections

Planning details

Reference
2360254
Local authority
Sligo County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
20 Sept 2023
Decision due
14 Nov 2023 · decided 14 Nov 2023
Decision
Conditional on 14 Nov 2023
Site area
337 m² from the mapped boundary, not the council's figure

Live near Main Street?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 4 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 30 Apr 2024 · Builder told the council work was starting CN0114665SO

Zoning

M1 — Metro / rail economic corridor

A high-density mixed-use employment corridor tied to a rail or metro line. Expect the tallest buildings in the area here.

Protections nearby 250 m

  • NIAH-recorded building · 9
    Arrow Lodge; house
  • Recorded monument · 2
    R159555; Bridge

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2360254 is a planning application to Sligo County Council for to construct a block of two semi-detached, 2.5 storey, 3-bedroom houses including, received on 20 Sept 2023; permission was granted with conditions on 14 Nov 2023.