Finisklin Business Park , , Co Sligo.
- 10 Sept 2024Received
- 30 Oct 2024Conditional
- 3 Dec 2024Final grant
- 2 Dec 2029Permission expires
- Status
- Granted with conditions
- Decision
- Conditional · 30 Oct 2024
- Council
- Sligo County Council
- Type
- PERMISSION
- Site
- 7.03 ha
What’s proposed
development, located to the northeast of the existing facility, will consist of a new ESB substation and switch room to serve the existing facility. The substation measures 45.7m2 in plan area and 3.5m in height. The switchroom and a back up generator will be located on a raised gantry that will measure 121m2 and 7m in height and be situated 3.5m above ground level
2460293 is a planning application to Sligo County Council for development, located to the northeast of the existing facility, will consist of a new, received on 10 Sept 2024; permission was granted with conditions on 30 Oct 2024.
Planning details
- Reference
- 2460293
- Local authority
- Sligo County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 10 Sept 2024
- Observations close
- 15 Oct 2024 (closed 704 days ago)
- Decision due
- 4 Nov 2024 · decided 30 Oct 2024
- Decision
- Conditional on 30 Oct 2024
- Proposed development
- development, located to the northeast of the existing facility, will consist of a new ESB substation and switch room to serve the existing facility. The substation measures 45.7m2 in plan area and 3.5m in height. The switchroom and a back up generator will be located on a raised gantry that will measure 121m2 and 7m in height and be situated 3.5m above ground levelAs published by the register.
- Site area
- 7.03 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 17 applications within 500 m in the last 5 years
- GrantedUnits 6 and 7 , Finisklin Road , Sligo
- WithdrawnUnits 6 and 7 , Finisklin Road , Sligo County Sligo
- WithdrawnUnit 2 Duncan Island Finisklin Sligo , Unit 2 Duncan Island Finisklin Sligo , Unit 2 Duncan Island Finisklin Sligo
- WithdrawnFinisklin Road , Finisklin , Co. Sligo
- WithdrawnUnit 2 Duncan Island Finisklin Sligo , Unit 2 Duncan Island Finisklin Sligo , Unit 2 Duncan Island Finisklin Sligo
- GrantedCarbury Point , Finisklin Industrial Estate , Finisklin Sligo
- GrantedUnit No 1 St Colms Centre , Finisklin , Sligo
- Appeal decidedDeepwater Quay , Sligo , Co. Sligo
Show all 17
- CommencedAn Post Sligo Delivery Service Unit , Finisklin Business Park Finisklin Sligo , County Sligo
- GrantedFinisklin Road , Finisklin Business Park , Sligo
- GrantedFinisklin Business Park , Finisklin , Sligo
- GrantedFinisklin Business Park , Finisklin , Sligo
- GrantedFinisklin Business Park , Sligo , F91 VY44
- GrantedFinisklin Business Park , Finisklin , Sligo
- CommencedFinisklin Business & Technology Park , Finisklin , Sligo
- GrantedFinisklin Business Park , Sligo
- CommencedUnit 10 St. Colm's Centre , Finisklin Business Park , Sligo
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
No other designation nearby.
Provenance
Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 461331). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/SligoCC/AppFileRefDetails/2460293/0.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |