Sligo County Council · 2660132
Hazelwood Demesne, Hazelwood, Sligo
Approved in Jul 2026. Building started in 2026.
- 8 Apr 2026Received
- 2 Jun 2026Conditional
- 6 Jul 2026Final approval
- 25 Sept 2026Building started
Planning details
- Status
- Building startedi
- Decision
- Conditional · 2 Jun 2026
- Reference
- 2660132
- Received
- 8 Apr 2026
- Units
- 1
- Site
- 1,883 m²
What’s proposed
Construct new detached dwelling house with onsite wastewater treatment system, connection to public services and all associated site works
5 other applications within 500 m in five years
Open the reportNearby 5 · 500 m · 5 years
Distance
Time
Homes nearby
- For saleKiltyccahill, Calry, Co. Sligo
- For saleKiltycahill, Hazelwood, Sligo, Co. Sligo, F91 AP26
- For saleVirgina Lodge, Barroe, Sligo, Co. Sligo, F91 F6P3
- WithdrawnSycamore Lodge, Hazelwood Road, Calry, Co. Sligo, F91 RHR1
- WithdrawnLake Wood, Hazelwood Road, Sligo, Co. Sligo, F91 T6P3
- WithdrawnGreen Road, Cairns Hill, Carraroe, Co. Sligo, F91 T9X5
Building started
- 25 Sept 2026 · Builder told the council work was starting (opted out of the finish sign-off) CN0147758SO
Zoning
G3 — High amenity
Protected high-amenity landscape. Development is resisted to preserve the character of the area.
Protections nearby 250 m
- Recorded monument · 2
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2660132 is a planning application to Sligo County Council for construct new detached dwelling house with onsite wastewater treatment system, received on 8 Apr 2026; permission was granted with conditions on 2 Jun 2026.