  1. 5 Nov 2021Received
  2. 11 Oct 2022Conditional
  3. 14 Nov 2022Final grant
  4. 13 Nov 2032Permission expires
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Granted with conditions
Decision
Conditional · 11 Oct 2022
Council
Tipperary County Council
Type
PERMISSION
Site
1.82 ha

What’s proposed

a ten-year appropriate period planning permission for development of this site: the proposed development will constitute the provision of the following: the installation of 2.25 km of 38kV underground grid connection comprising cable ducting and associated electrical cabling and all other ancillary works including joint bays, culverts, maker posts and all associated developments. Advisory Note: The full extent of the grid connection is 33.8 km, and a separate planning application will be made for a underground grid connection to Kilkenny County Council. This development comprises part of an overall development for which planning permission was granted for a 9 turbine wind farm and all associated works on lands located in the townlands of Farranrory Upper, Farranrory Lower, Coolnashinnagh and Gortnasmuttaun, Co. Tipperary. The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement

211620 is a planning application to Tipperary County Council for a ten-year appropriate period planning permission for development of this site: the, received on 5 Nov 2021; permission was granted with conditions on 11 Oct 2022.

Planning details

Reference
211620
Local authority
Tipperary County Council
Status
Granted with conditions · register status “APPLICATION FINALISED”
Received
5 Nov 2021
Observations close
10 Dec 2021 (closed 1752 days ago)
Decision due
17 Oct 2022 · decided 11 Oct 2022
Decision
Conditional on 11 Oct 2022
Proposed development
a ten-year appropriate period planning permission for development of this site: the proposed development will constitute the provision of the following: the installation of 2.25 km of 38kV underground grid connection comprising cable ducting and associated electrical cabling and all other ancillary works including joint bays, culverts, maker posts and all associated developments. Advisory Note: The full extent of the grid connection is 33.8 km, and a separate planning application will be made for a underground grid connection to Kilkenny County Council. This development comprises part of an overall development for which planning permission was granted for a 9 turbine wind farm and all associated works on lands located in the townlands of Farranrory Upper, Farranrory Lower, Coolnashinnagh and Gortnasmuttaun, Co. Tipperary. The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement
As published by the register.
Site area
1.82 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 2 applications within 500 m in the last 5 years

Explore this area on the map →

Appeal

Not appealed.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    No zoning objective covers this site in the current plan.

    Designations within 250 m

    No OPW flood extent nearby.

    No other designation nearby.

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 469696). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/TipperaryCC/AppFileRefDetails/211620/0.

    Source: npad · fetched 18 Sept 2026, 15:44
    SourceLicenceFetchedLink
    npadCC-BY-4.018 Sept 2026, 15:44open