PlanningRegister.ie
Tipperary County Council · 21875

Bouladuff, Thurles, Co. Tipperary

Approved in Feb 2022. No sign of building yet.

Start notices are matched from the national building control register; a start on site can be missed.

What’s proposed

A residential development consisting of an internal roadway, footpaths, lighting and all associated services for 6 no. serviced residential sites each with its own independent on site waste water treatment system, the proposed includes for the use of a previously constructed entrance which was developed further to planning permission 05510502 and for permission to create necessary sightlines at the entrance and to carry out all associated works

  1. 16 Jun 2021Received
  2. 5 Jan 2022Conditional
  3. 8 Feb 2022Final approval
  4. 7 Feb 2027Approval runs out

An email when the builder tells the council work is starting.

Planning details

Status
Approved
Decision
Conditional · 5 Jan 2022
Reference
21875
Received
16 Jun 2021
Further information
Requested 10 Aug 2021 · received 1 Dec 2021
Units
1
Site
1.68 ha

1 other application within 500 m in the last year

Get the full report

Nearby 1 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Zoning

S5 — Sustainable neighbourhood infrastructure

Reserved for the schools, creches, community and health facilities a neighbourhood needs.

Protections nearby 250 m

  • Recorded monument · 3
    R136828; Barrow - mound barrow
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

21875 is a planning application to Tipperary County Council for a residential development consisting of an internal roadway, footpaths, lighting and all, received on 16 Jun 2021; permission was granted with conditions on 5 Jan 2022.