Tipperary County Council · 2360104
Birdhill, Co. Tipperary
Approved in May 2023. Building started in 2024.
- 17 Feb 2023Received
- 6 Apr 2023Conditional
- 10 May 2023Final approval
- 1 Feb 2024Building started
- Status
- Building startedi
- Decision
- Conditional · 6 Apr 2023
- Council
- Tipperary County Council
- Type
- PERMISSION CONSEQUENT
- Units
- 2
- Site
- 2,133 m²
What’s proposed
to demolish existing dwelling house & shed and replace with a new dwelling house & garage, upgrade existing waste water treatment system & construct a new entrance along with all ancillary site works
Planning details
- Reference
- 2360104
- Local authority
- Tipperary County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 17 Feb 2023
- Decision due
- 13 Apr 2023 · decided 6 Apr 2023
- Decision
- Conditional on 6 Apr 2023
- Site area
- 2,133 m² from the mapped boundary, not the council's figure
Nearby 4 · 500 m · 12 months
Distance
Time
- Awaiting decisionBirdhill , Co. Tipperary
- WithdrawnBirdhill , Co. Tipperary
- CommencedBirdhill , Co Tipperary
- WithdrawnBirdhill , Co Tipperary
Building started
- 31 Aug 2026 · Builder told the council work was starting (opted out of the finish sign-off) CN0146562TT
- 1 Feb 2024 · Builder told the council work was starting (opted out of the finish sign-off) CN0109206TT
- 1 Feb 2024 · Builder told the council small works were starting CN0109207TT
Protections nearby 250 m
- NIAH-recorded building · 4
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary