Approved in Oct 2024. Building started in 2024.

  1. 19 Jun 2024Received
  2. 27 Sept 2024Conditional
  3. 31 Oct 2024Final approval
  4. 19 Nov 2024Building started

Planning details

Status
Building startedi
Decision
Conditional · 27 Sept 2024
Reference
2460491
Received
19 Jun 2024
Further information
Requested 13 Aug 2024 · received 3 Sept 2024
Units
1
Site
1,685 m²

What’s proposed

The construction of a dwelling, garage, effluent treatment system, entrance and all associated site works

2 other applications within 500 m in the last year

Open the report

Nearby 2 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Building started

  • 19 Nov 2024 · Builder told the council work was starting (opted out of the finish sign-off) CN0122053TT

Protections nearby 250 m

  • Recorded monument · 1
    R134887
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2460491 is a planning application to Tipperary County Council for the construction of a dwelling, garage, effluent treatment system, entrance and all, received on 19 Jun 2024; permission was granted with conditions on 27 Sept 2024.