Knockcurraghbola Commons, Upperchurch, Co. Tipperary
Approved in Jan 2025. Building started in 2026.
- 18 Oct 2024Received
- 5 Dec 2024Conditional
- 8 Jan 2025Final approval
- 2 Feb 2026Building started
Planning details
- Status
- Building startedi
- Decision
- Conditional · 5 Dec 2024
- Reference
- 2460901
- Received
- 18 Oct 2024
- Site
- 1.34 ha
What’s proposed
The amendments to Upperchurch Windfarm Electrical Substation authorised under An Bord Pleanála Ref. No. Pl.22.243040 and PA92.310171. The amendments consist of a) increase in size of the substation compound yard; b) change to the layout of electrical equipment in the substation compound yard; c) change in size, design and increase in height of the two control buildings and d) ancillary works. The application is accompanied by an Appropriate Assessment Report (stage 1 – screening) and screening for Environmental Impact Assessment (EIA) report
2 other applications within 500 m in the last year
Open the reportNearby 2 · 500 m · 12 months
Building started
- 15 Apr 2026 · Builder told the council work was starting (seven-day notice) SN0014028TT
- 2 Feb 2026 · Builder told the council work was starting (seven-day notice) SN0013672TT
Protections nearby 250 m
- Recorded monument · 4
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2460901 is a planning application to Tipperary County Council for the amendments to Upperchurch Windfarm Electrical Substation authorised under An Bord, received on 18 Oct 2024; permission was granted with conditions on 5 Dec 2024.