Rehill, Ballylooby, County Tipperary
Approved in Sept 2025. Building started in 2025.
- 4 Jul 2025Received
- 22 Aug 2025Conditional
- 25 Sept 2025Final approval
- 23 Dec 2025Building started
Planning details
- Status
- Building startedi
- Decision
- Conditional · 22 Aug 2025
- Reference
- 2560639
- Received
- 4 Jul 2025
- Site
- 5,626 m²
What’s proposed
1) a dormer type extension to existing dwelling house, 2) part demolition of the existing house and the refurbishment of the remaining dwelling including revised fenestration, 3) domestic garage, 4) new wastewater system to replace existing septic tank, 5) upgrading of existing vehicular entrance, 6) RETENTION of a mobile home and completed site works (stone infill area) for the duration of the build and all proposed associated site works
1 other application within 500 m in the last year
Open the reportNearby 1 · 500 m · 12 months
Homes nearby
Building started
- 23 Dec 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0136824TT
Protections nearby 250 m
- Recorded monument · 3
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2560639 is a planning application to Tipperary County Council for 1) a dormer type extension to existing dwelling house, 2) part demolition of the, received on 4 Jul 2025; permission was granted with conditions on 22 Aug 2025.