Tipperary County Council · 2560775
Barravie, Capparoe Nenagh, Co. Tipperary
Approved in Nov 2025. Building started in 2025.
- 7 Aug 2025Received
- 30 Sept 2025Conditional
- 3 Nov 2025Final approval
- 2 Dec 2025Building started
- Status
- Building startedi
- Decision
- Conditional · 30 Sept 2025
- Council
- Tipperary County Council
- Type
- PERMISSION
- Units
- 1
- Site
- 5,985 m²
What’s proposed
the construction of an entrance, dwelling house, garage, domestic waste water treatment system with polishing filter together with all associated site works
Planning details
- Reference
- 2560775
- Local authority
- Tipperary County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 7 Aug 2025
- Decision due
- 1 Oct 2025 · decided 30 Sept 2025
- Decision
- Conditional on 30 Sept 2025
- Site area
- 5,985 m² from the mapped boundary, not the council's figure
Nearby 4 · 500 m · 5 years
Distance
Time
Homes nearby
Building started
- 2 Dec 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0136256TT
Protections nearby 250 m
- Recorded monument · 2
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2560775 is a planning application to Tipperary County Council for the construction of an entrance, dwelling house, garage, domestic waste water treatment, received on 7 Aug 2025; permission was granted with conditions on 30 Sept 2025.