  1. 12 Mar 2026Received
  2. 9 Sept 2026Conditional
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Granted with conditions
Decision
Conditional · 9 Sept 2026
Council
Tipperary County Council
Type
PERMISSION
Site
3.15 ha

What’s proposed

(RED III) development will consist of; laying of underground 33kV medium voltage electrical cables, 6 no. joint bays, with associated ducting and ancillary development. The cables will be laid under public roads and private lands within the townlands of Clohoge and Graigue Co. Tipperary, with c. 860m within the L-4156 and c. 540m within the L-41561 public road and c. 1,092m located on private agricultural land within the townland of Graigue. The underground cable is intended to connect the permitted Killough Solar Farm, approved by Tipperary County Council (Pl. Ref. 2560003), and An Coimisiún Pleanála (Ref No. 323453-25), to a proposed 110kV Gas Insulated Switchgear (GIS) substation, which will be subject to a separate application for consent to An Coimisiún Pleanála. Temporary alternative access to residential properties on the L-41561 will be provided during the laying of the cable, provided by an existing access track on lands in the townland of Graigue which will connect to the future access track associated with the substation site, allowing direct access to the L-4156 from the L-41561 for the duration of the construction period. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the Application. Permission is sought for a period of 10 years

2660228 is a planning application to Tipperary County Council for (RED III) development will consist of; laying of underground 33kV medium voltage, received on 12 Mar 2026; permission was granted with conditions on 9 Sept 2026.

Planning details

Reference
2660228
Local authority
Tipperary County Council
Status
Granted with conditions · register status “DECISION MADE”
Received
12 Mar 2026
Observations close
16 Apr 2026 (closed 167 days ago)
Decision due
9 Sept 2026 · decided 9 Sept 2026
Decision
Conditional on 9 Sept 2026
Proposed development
(RED III) development will consist of; laying of underground 33kV medium voltage electrical cables, 6 no. joint bays, with associated ducting and ancillary development. The cables will be laid under public roads and private lands within the townlands of Clohoge and Graigue Co. Tipperary, with c. 860m within the L-4156 and c. 540m within the L-41561 public road and c. 1,092m located on private agricultural land within the townland of Graigue. The underground cable is intended to connect the permitted Killough Solar Farm, approved by Tipperary County Council (Pl. Ref. 2560003), and An Coimisiún Pleanála (Ref No. 323453-25), to a proposed 110kV Gas Insulated Switchgear (GIS) substation, which will be subject to a separate application for consent to An Coimisiún Pleanála. Temporary alternative access to residential properties on the L-41561 will be provided during the laying of the cable, provided by an existing access track on lands in the townland of Graigue which will connect to the future access track associated with the substation site, allowing direct access to the L-4156 from the L-41561 for the duration of the construction period. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the Application. Permission is sought for a period of 10 years
As published by the register.
Site area
3.15 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 1 application within 500 m in the last 5 years

Explore this area on the map →

Homes nearby

Appeal

Not appealed.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    No zoning objective covers this site in the current plan.

    Designations within 250 m

    No OPW flood extent nearby.

    • Recorded monument · 8
      R136477; R136483; R136492

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 476607). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/TipperaryCC/AppFileRefDetails/2660228/0.

    Source: npad · fetched 18 Sept 2026, 15:44
    SourceLicenceFetchedLink
    npadCC-BY-4.018 Sept 2026, 15:44open