ESB Doon 110 kV Substation, Ballyvaughan, Clonmel Co. Tipperary
Approved in Nov 2026.
What’s proposed
RED III development which will consist of the provision of new electrical plant and equipment, including; 1 no. existing Arc Suppression Coil to be retired and replace with 1 no. new Arc Suppression Coil, extension to control room building (c. 27 m2), associated and ancillary outdoor electrical equipment and other apparatus, including installation of underground cables; and all other ancillary works.
Show all
(This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply)
- 3 Jul 2026Received
- 6 Oct 2026Conditional
- 9 Nov 2026Final approval
- 8 Nov 2031Approval runs out
Planning details
- Status
- Approved
- Decision
- Conditional · 6 Oct 2026
- Reference
- 2660648
- Received
- 3 Jul 2026
- Site
- 1.24 ha
3 other applications within 500 m in five years
Get the full reportNearby 3 · 500 m · 5 years
Homes nearby
Zoning
Land zoned to stay rural. New houses are restricted to demonstrated local need under the rural-housing policy of the development plan.
Where this comes from
National planning feed (NPAD), fetched 11 Nov 2026, 23:00.
Source: National Planning Application Database · fetched 11 Nov 2026, 23:00
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 11 Nov 2026, 23:00 | open |
Summary
2660648 is a planning application to Tipperary County Council for RED III development which will consist of the provision of new electrical plant and, received on 3 Jul 2026; permission was granted with conditions on 6 Oct 2026.