Waterford City and County Council · 1796
Cooltubbrid West, Kilmacthomas, Co. Waterford
Decided on appeal: granted.
- 14 Feb 2017Received
- 6 Apr 2017Refused
- 12 Mar 2023Approval runs out
- Status
- Appeal decided — granted
- Decision
- Refused · 6 Apr 2017
- Council
- Waterford City and County Council
- Type
- PERMISSION
- Site
- 10.73 ha
What’s proposed
proposed works will include a 4.2MVA solar farm comprising photovoltaic panels on ground mounted frames, four single storey inverter/transformer stations, one single storey terminal station, one single storey electrical switchroom, security fencing, CCTV and all associated ancillary development works
Planning details
- Reference
- 1796
- Local authority
- Waterford City and County Council
- Status
- Appeal decided — granted · register status “APPLICATION FINALISED”
- Received
- 14 Feb 2017
- Observations close
- 21 Mar 2017 (closed 3501 days ago)
- Decision due
- 10 Apr 2017 · decided 6 Apr 2017
- Decision
- Refused on 6 Apr 2017
- Site area
- 10.73 ha from the mapped boundary, not the council's figure
Nearby 2 · 500 m · 5 years
Homes nearby
- For saleCooltubrid House On Approx.11acres, Cooltubrid East, Kilmacthomas, Co. Waterford, X42 HK19
- For saleCooltubrid House On Approx.11acres, Cooltubrid East, Kilmacthomas, Co. Waterford, X42 HK19
- For saleTeac Coillte, Ahanaglogh, Kilmacthomas, Co. Waterford, X42 E227
- For saleLeargán, Kilmacthomas, Co. Waterford
- Withdrawn46 Cruachan View, Kilmacthomas, Co. Waterford, X42 K657
- WithdrawnGarranturton, Kilmacthomas, Co. Waterford, X42 CX98
Appeal
Appeal PL24.248413 (status unknown), not yet matched.
Protections nearby 250 m
- Recorded monument · 7
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
1796 is a planning application to Waterford City and County Council for proposed works will include a 4.2MVA solar farm comprising photovoltaic panels on ground, received on 14 Feb 2017; permission was refused on 6 Apr 2017.