Westmeath County Council · 21673
Hopestown, Ballinea, Mullingar
Approved in May 2022. Building started in 2024.
- 20 Dec 2021Received
- 11 Apr 2022Conditional
- 25 May 2022Final approval
- 5 Jul 2024Building started
Planning details
- Status
- Building startedi
- Decision
- Conditional · 11 Apr 2022
- Reference
- 21673
- Received
- 20 Dec 2021
- Further information
- Requested 16 Feb 2022 · received 22 Mar 2022
- Units
- 1
- Site
- 3,416 m²
What’s proposed
To construct a dwelling house and detached garage with treatment system and percolation area with all ancillary site works
4 other applications within 500 m in five years
Open the free reportNearby 4 · 500 m · 5 years
Distance
Time
Homes nearby
Building started
- 5 Jul 2024 · Builder told the council work was starting (opted out of the finish sign-off) CN0116709WH
Protections nearby 250 m
- NIAH-recorded building · 2
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
21673 is a planning application to Westmeath County Council for to construct a dwelling house and detached garage with treatment system and percolation, received on 20 Dec 2021; permission was granted with conditions on 11 Apr 2022.