Townlands of, Parcellstown and Shanonagh, Mullingar
Approved in Oct 2022. No sign of building yet.
Start notices are matched from the national building control register; a start on site can be missed.
What’s proposed
The development will consist of planning permission for a period of 10 years to construct and complete a Solar PV Energy Development with a total site area of 42.06 hectares, to include a single storey electrical substation building, inverter substations, modules, solar PV ground mounted on support structures, a temporary construction compound, internal access tracks, security fencing, electrical cabling and ducting…
Show all
CCTV and other ancillary infrastructure, drainage, additional landscaping and habitat enhancement as required and associated site development works. The solar farm will be operational for 35-years
- 14 Mar 2022Received
- 1 Sept 2022Conditional
- 6 Oct 2022Final approval
- 5 Oct 2032Approval runs out
Planning details
- Status
- Approved
- Decision
- Conditional · 1 Sept 2022
- Reference
- 22113
- Received
- 14 Mar 2022
- Further information
- Requested 6 May 2022 · received 5 Aug 2022
- Site
- 42.15 ha
3 other applications within 500 m in five years
Get the full reportNearby 3 · 500 m · 5 years
Homes nearby
Protections nearby 250 m
- NIAH-recorded building · 1
- Recorded monument · 9
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
22113 is a planning application to Westmeath County Council for the development will consist of planning permission for a period of 10 years to, received on 14 Mar 2022; permission was granted with conditions on 1 Sept 2022.