Proposed development which will consist of: a high-power electric vehicle charging hub and associated infrastructure to comprise of the following: (i) installation of 4no. electric vehicle charging bays and 2no. charge points, (ii) installation of new canopy with associated illuminated signage, (iii) new modular ESB Substation, (iv), new EV banner sign and (v) all other associated site development and drainage works

  1. 19 Dec 2024Received
  2. 20 Feb 2025Conditional
  3. 28 Mar 2025Final approval
  4. 27 Mar 2030Approval runs out

An email when the builder tells the council work is starting.

Planning details

Status
Approved
Decision
Conditional · 20 Feb 2025
Reference
2460490
Received
19 Dec 2024
Site
4,263 m²

1 other application within 500 m in five years

Get the full report

Nearby 1 · 500 m · 5 years

Distance
Time

Explore this area on the map →

Homes nearby

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2460490 is a planning application to Westmeath County Council for proposed development which will consist of: a high-power electric vehicle charging hub, received on 19 Dec 2024; permission was granted with conditions on 20 Feb 2025.