PlanningRegister.ie
Wexford County Council · 20220518

Knockduff (ed Tinnacross), Tinnacross

Approved in Sept 2022. Building started in 2023.

  1. 21 Apr 2022Received
  2. 3 Aug 2022Approved
  3. 5 Sept 2022Final approval
  4. 3 Mar 2023Building started

Planning details

Status
Building startedi
Decision
Approved (conditional) · 3 Aug 2022
Reference
20220518
Received
21 Apr 2022
Further information
Requested 3 Jun 2022 · received 8 Jul 2022
Units
1
Site
3,855 m²

What’s proposed

Permission to construct a fully serviced dwelling house with associated site

1 other application within 500 m in the last year

Open the report

Nearby 1 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 3 Mar 2023 · Builder told the council work was starting (opted out of the finish sign-off) CN0098245WX
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

20220518 is a planning application to Wexford County Council for permission to construct a fully serviced dwelling house with associated site, received on 21 Apr 2022; permission was granted with conditions on 3 Aug 2022.