PlanningRegister.ie
Wexford County Council · 20221053

Carraig Mhor, Maudlintown

Approved in Jul 2023. Building started in 2023, signed off as finished in Jun 2025.

The homes here are sold as Carraig Mhor.

  1. 3 Aug 2022Received
  2. 31 May 2023Approved
  3. 3 Jul 2023Final approval
  4. 1 Aug 2023Building started
  5. 25 Jun 2025Signed off

Planning details

Status
Building started
Decision
Approved (conditional) · 31 May 2023
Reference
20221053
Received
3 Aug 2022
Further information
Requested 16 Sept 2022 · received 5 May 2023
Units
28
Site
1.54 ha

What’s proposed

Permission for a residential development to be completed over 3 phases

6 other applications within 500 m in the last year

Open the report

Nearby 6 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 15 Apr 2024 · Builder told the council work was starting CN0114399WX
  • 29 Jan 2024 · Builder told the council work was starting CN0109208WX
  • 1 Aug 2023 · Builder told the council work was starting CN0104297WX

Protections nearby 250 m

  • NIAH-recorded building · 15
    house; Maudlintown
  • Recorded monument · 6
    R134518; R134519
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

20221053 is a planning application to Wexford County Council for permission for a residential development to be completed over 3 phases, received on 3 Aug 2022; permission was granted with conditions on 31 May 2023.