PlanningRegister.ie
Wexford County Council · 20240795

Courtnacuddy, Castleboro

Approved in 2024. Building started in 2025.

  1. 5 Jul 2024Received
  2. 11 Oct 2024Approved
  3. 13 Nov 2024Final approval
  4. 11 Feb 2025Building started
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Building startedi
Decision
Approved (conditional) · 11 Oct 2024
Council
Wexford County Council
Type
Permission
Site
2,629 m²

Live near Courtnacuddy?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

Permission for the erection of a fully serviced new dwelling together with

Planning details

Reference
20240795
Local authority
Wexford County Council
Status
Commenced · register status “n/a”
Received
5 Jul 2024
Observations close
9 Aug 2024 (closed 789 days ago)
Decision due
17 Oct 2024 · decided 11 Oct 2024
Decision
Granted (conditional) on 11 Oct 2024
Proposed development
Permission for the erection of a fully serviced new dwelling together with
As published by the register.
Site area
2,629 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 2 · 500 m · 5 years

Explore this area on the map →

Building started

  • 11 Feb 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0125648WX

Zoning

Not zoned in the current plan.

Protections nearby 250 m

No mapped flood area nearby.

  • NIAH-recorded building · 2
    Catholic Church of Our Lady and Saint Carthage; post box
  • Radon risk area · 1
    About 1 in 10 homes in this area is likely to have high radon levels

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

20240795 is a planning application to Wexford County Council for permission for the erection of a fully serviced new dwelling together with, received on 5 Jul 2024; permission was granted with conditions on 11 Oct 2024.