Approved in Nov 2025. Building started in 2026.
- 14 Aug 2025Received
- 24 Oct 2025Approved
- 26 Nov 2025Final approval
- 4 Aug 2026Building started
Planning details
- Status
- Building startedi
- Decision
- Approved (conditional) · 24 Oct 2025
- Reference
- 20251001
- Received
- 14 Aug 2025
- Further information
- Requested 3 Oct 2025 · received 7 Oct 2025
- Units
- 1
- Site
- 3,923 m²
What’s proposed
Permission for the erection of a fully serviced
1 other application within 500 m in the last year
Open the reportNearby 1 · 500 m · 12 months
Distance
Time
Homes nearby
Building started
- 4 Aug 2026 · Builder told the council work was starting (opted out of the finish sign-off) CN0145783WX
Protections nearby 250 m
- Recorded monument · 2
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
20251001 is a planning application to Wexford County Council for permission for the erection of a fully serviced, received on 14 Aug 2025; permission was granted with conditions on 24 Oct 2025.