211351 is a planning application for permission at Unit 3 Lathaleer Industrial Park , Baltinglass , Co. Wicklow, received by Wicklow County Council on 11 Nov 2021 and first seen by Planning Register on 11 Sept 2026. The application describes: construction of single storey side extension comprising ESB substation and switch room (53m2), new internal mezzanine plant area (56.6m2) with stairs, internal alterations to include new room layouts and repositioning existing stairs, 3 no. new windows and 2 no. new signs and relocated roller shutter door all to front elevation, 1 no. new window and replace door to side elevation. 4 no. fire doors, new steps and guarding. 2 no. external 8m high water storage tanks, 3 no. external cooling towers on concrete plinths with acoustic walls 6m high, revision to parking area and landscaping and changes to foul and storm water drainage on the site and associated works. The council granted permission on 26 Apr 2022, with conditions. The five-week observation window closed on 16 Dec 2021. Within 500 m there is 1 other decided application in the last five years.
Proposal
construction of single storey side extension comprising ESB substation and switch room (53m2), new internal mezzanine plant area (56.6m2) with stairs, internal alterations to include new room layouts and repositioning existing stairs, 3 no. new windows and 2 no. new signs and relocated roller shutter door all to front elevation, 1 no. new window and replace door to side elevation. 4 no. fire doors, new steps and guarding. 2 no. external 8m high water storage tanks, 3 no. external cooling towers on concrete plinths with acoustic walls 6m high, revision to parking area and landscaping and changes to foul and storm water drainage on the site and associated works
- Status
- APPLICATION FINALISED
- Decision
- Conditional on 26 Apr 2022
- Final grant
- 30 May 2022
- Permission expires
- 29 May 2027
- Site (from polygon)
- 3,938 m²
- Location precision
- site (coords_polygon)
Timeline
- 11 Nov 2021New applicationObservation window closed 16 Dec 2021
- 11 Jan 2022Further information requested
- 25 Jan 2022Further information received
- 26 Apr 2022DecisionAppeal window closed 24 May 2022

Full planning report for 52.93794, -6.69172
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
- Radon risk area · 1
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 159538). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/WicklowCC/AppFileRefDetails/211351/0.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |