No decision yet (was due 14 Sept 2021).

  1. 21 Jul 2021Received
  2. 14 Sept 2021Decision due

An email when it’s decided. After that, only if it’s appealed or building starts.

Planning details

Status
With the council, no decision yet
Decision
Due 14 Sept 2021
Reference
21869
Received
21 Jul 2021
Site
4.25 ha

What’s proposed

Part 8 - Process for the Bray Sustainable Transport Bridge Project - The proposed bridge and link road will consist of a two-lane public transport road 3.25m wide and variable width pedestrian, cyclist and shared path facilities. A new pedestrian boardwalk is proposed along the southern bank wall to link the existing walkway to the bridge crossing

37 other applications within 500 m in the last year

Open the report

Nearby 37 · 500 m · 12 months

Distance
Time
Show all 37

Explore this area on the map →

Homes nearby

Zoning

G1 — Open space with recreation

Open space with active recreational amenities — pitches, courts, play areas.

M5 — Mixed use — outer core

A mix of uses complementing a town centre, with less retail and residential than the core itself.

N6 — Strategic infrastructure

Land tied to a national or strategic asset (airport, port, rail corridor). Uses are controlled by that asset's own plan.

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

Flood area nearby (OPW maps). floodinfo.ie ↗

  • NIAH-recorded building · 40
    building misc; house
  • Recorded monument · 7
    Linear earthwork; R181220
Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

21869 is a planning application to Wicklow County Council for part 8 - Process for the Bray Sustainable Transport Bridge Project - The proposed bridge, received on 21 Jul 2021; a decision is due by 14 Sept 2021.