Bagenalstown Industrial Park , Royal Oak Road , Muine Bheag

Construction of a new foul water pumping station comprising an underground wet well/dry well, package pumping plant, above-ground kiosk/control panel, security fencing, site access, connection to the existing public foul sewer network, and all associated works to facilitate the development

Observations close 18 Nov 2026 closes today
5 weeks from receipt (received 14 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 8 Dec 2026

The application

Reference
2660314 · full record
Authority
Carlow County Council
Type
PERMISSION
Status
NEW APPLICATION
Site area
1,637 m²
Received
14 Oct 2026
Decision due
8 Dec 2026

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/CarlowCC/AppFileRefDetails/2660314/0.
  2. Write your observation.Quote 2660314 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Carlow County Council takes it online with the submission or at the counter.
  4. Submit before 18 Nov 2026.Online through the register above, or in writing to the Planning Department, Carlow County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
C6
Waterfront
Industry and Warehousing: To provide for industrial development and ancillary office use and warehousing usescarlow county development plan 2022 2028 variation number 2 muine bheag royal oak district town plan 20264 Jul 2022 → 3 Jul 2028
C6
Waterfront
Industry and Warehousing: To provide for industrial development and ancillary office use and warehousing usescarlow county development plan 2022 2028 variation number 2 muine bheag royal oak district town plan 20264 Jul 2022 → 3 Jul 2028
C6
Waterfront
Industry and Warehousing: To provide for industrial development and ancillary office use and warehousing usescarlow county development plan 2022 2028 variation number 2 muine bheag royal oak district town plan 20264 Jul 2022 → 3 Jul 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: Carlow County Council development plan zoning · fetched 27 Sept 2026, 19:37
SourceLicenceFetchedLink
Carlow County Council development plan zoning—27 Sept 2026, 19:37open

Designations on or near the site within 100 m

  • Recorded monument × 2
    Excavation - miscellaneous · R145239

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2660081Conditional15 Jul 20260 mthe construction of a 9920m2 light industrial unit incorporating: a single-storey light industrial building; training and warehouse annex with mezzanine; two-storey office and support facilities annex; associated car and bicycle parking and loading areas; two vehicle entrances; completing the existing industrial park access road (as previously permitted under Permission 19/313) with underground services; connection to existing drainage and water infrastructure; hard and soft landscaping and boundary treatments; and all associated works to facilitate the development
2560271Conditional31 Oct 20250 man extension to existing industrial unit and ancillary office accommodation, retention permission for existing dry store, along with concrete yards and all ancillary works
2560065Conditional8 May 20251468 mthe as-built revision to the front elevation
2360154Conditional6 Jun 2024210 mpermission is sought for the construction of an industrial storage unit with all associated site works, constructed to rear of existing industrial unit.
2360122Conditional19 Apr 2024324 mPlanning permission is sought for the construction of an industrial storage unit with all associated site works, constructed to rear of existing industrial unit
22402Conditional13 Jul 2023330 mfor (a) the erection of 3 no. water tanks having maximum height of 12 meters above ground level. (b) the relocation of 2 no. existing grain silos and all associated site works
22320Conditional18 Nov 2022468 mthe construction of a portal frame storage unit with the installation of solar photovoltaic panels mounted to roof of same, with all associated ancillary site development works
22249Conditional20 Sept 2022330 mthe installation of solar photovoltaic panels mounted to roof of existing portal frame building and all associated site works

What has happened on this file

  • 14 Oct 2026 New application · observations close 18 Nov 2026
  • 14 Oct 2026 Decision