Clonlea , Kilkishen , Co Clare

for the following: 1) to retain and complete partially constructed houses No's 1 and 2, 2) permission to construct house No's 3, 4 and 5 and connect to public water and sewer services all as granted under previously planning permissions P19-810 and P22-10 plus all ancillary site works

Observations close 14 Oct 2026 24 days left
5 weeks from receipt (received 9 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee 20 · council decision due 3 Nov 2026

The application

Reference
26244 · full record
Authority
Clare County Council
Type
PERMISSION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
5
Floor area
5 m²
Site area
4,580 m²
Received
9 Sept 2026
We first saw it
18 Sept 2026, 15:44
Decision due
3 Nov 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/ClareCC/AppFileRefDetails/26244/0.
  2. Write your observation.Quote 26244 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Clare County Council takes it online with the submission or at the counter.
  4. Submit before 14 Oct 2026.Online through the register above, or in writing to the Planning Department, Clare County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

Nothing designated within 100 m of the site.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2560681Conditional24 Apr 20261269 mfor the construction of a two storey detached dwelling house with a single storey detached garage including new entrance gates and piers, hard and soft landscaping, new front boundary wall, connections to public sewer/services and all ancillary site works
2560679Conditional24 Apr 20261250 mfor the construction of a two storey detached dwelling house with a single storey detached garage including new entrance gates and piers, hard and soft landscaping, new front boundary wall, connections to public sewer/services and all ancillary site works
2560726Conditional27 Jan 20260195 mfor the construction of amendments to the existing site entrance to our lands at Teeronea, Kilkishen, Co. Clare. This application seeks permission for the construction of amendments to the existing site entrance including permission for partial removal of existing hedgerow and boundary walls, widening and re-profiling for improved sight lines for vehicular access, a new pedestrian entrance/s and footpaths, provision of site services, site lighting and all ancillary site works
2560174Refused27 Aug 20251310 mfor the construction of a two storey detached dwelling house with a single storey detached garage including new entrance gates and piers, hard and soft landscaping, new front boundary wall, connections to public sewer and all ancillary site works
2560173Refused27 Aug 20251345 mfor the construction of a two storey detached dwelling house with a single storey detached garage including new entrance gates and piers, hard and soft landscaping, new front boundary wall, connections to public sewer and all ancillary site works
2460637Conditional17 Apr 20254498 mfor the construction of a residential development consisting of 4 no. 2 bedroom apartment units, connection to services and all associated site works
2560060Conditional3 Apr 20250119 mfor the erection of LED floodlighting mounted on 4 No. columns to the existing all-weather pitch with all associated site works
2446Conditional15 Nov 20240452 mof changes made to the front elevation of the existing dwelling at first floor level and increasing roof height and also retain change of use from commercial to residential with associated site works

Appeals

ACP caseTypeOutcomeDecidedDistance
319125Refused10 Mar 2025136 m
312376Refused20 Jul 2022310 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 9 Sept 2026 New application · observations close 14 Oct 2026
  • 9 Sept 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 18 Sept 2026, 15:44. Not legal advice — confirm the deadline with Clare County Council before relying on it.