Lands at Manusmore and Carrownanelly , Clarecastle , Co. Clare

to Extend the Appropriate Period of Planning Permission P21/915. A Solar PV Energy development with a total site area of 16.08 hectares, to include inverter station modules, solar PV panels ground mounted on support structures, internal access tracks, watercourse crossing, security fencing, electrical cabling and ducting, CCTV and other ancillary infrastructure, drainage, additional landscaping and habitat enhancement and associated site development works relating to the access to the site

Observations close 28 Oct 2026 15 days left
5 weeks from receipt (received 23 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 17 Nov 2026

The application

Reference
26262 · full record
Authority
Clare County Council
Type
EXTENSION OF DURATION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
0
Floor area
—
Site area
16.35 ha
Received
23 Sept 2026
We first saw it
29 Sept 2026, 23:03
Decision due
17 Nov 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/ClareCC/AppFileRefDetails/26262/0.
  2. Write your observation.Quote 26262 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Clare County Council takes it online with the submission or at the counter.
  4. Submit before 28 Oct 2026.Online through the register above, or in writing to the Planning Department, Clare County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

  • Recorded monument × 2
    Excavation - miscellaneous · R119825

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
25291Unconditional3 Nov 202500 mto Extend the Appropriate Period of Planning permission for P20/562 the development will consist of a planning permission for a period of 5 years to construct and complete a Solar PV Energy development with a total site area of 99.2 hectares, to include a single storey electrical substation building, electrical transformer and invertor station modules, solar PV panels ground mounted on support structures, internal access tracks, security fencing, electrical cabling and ducting, CCTV and other ancillary infrastructure, drainage, additional landscaping and habitat enhancement as required and associated site development works including works relating to the access to the site. The Solar farm will be operational for 35 years. A Natura Impact Statement has been prepared in respect of this planning application
22586Conditional9 Mar 20230364 mfor development at this site in the townlands of Ballyvonnavaum TD, Coolshamroge TD, Cloonmore TD, Deerpark TD, and Manusmore TD, Ennis, Co Clare. The development will consist of planning permission for a period of 10 years to construct and complete a Solar PV Energy development with a total site area of 27.34 hectares, to include inverter station modules, solar PV panels ground mounted on support structures, internal access tracks, security fencing, electrical cabling and ducting, CCTV and other ancillary infrastructure, drainage, additional landscaping and habitat enhancement as required and associated site development works including works relating to the access to the site. The solar farm would be operational for 35 years. A Natura Impact Statement has been prepared in respect to the application for planning permission
21915Conditional21 Oct 202110 mthe development will consist of planning PERMISSION for a period of five years to construct and complete a Solar PV Energy development with a total site area of 16.08 hectares, to include inverter station modules, solar PV panels ground mounted on support structures, internal access tracks, watercourse crossing, security fencing, electrical cabling and ducting, CCTV and other ancillary infrastructure, drainage, additional landscaping and habitat enhancement as required and associated site development works including works relating to the access to the site. The solar farm would be operational for 35 years. A Natura Impact Statement has been prepared in respect of this planning application

Appeals

No appeals within 500 m in the last 5 years.

What has happened on this file

  • 23 Sept 2026 New application · observations close 28 Oct 2026
  • 23 Sept 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 29 Sept 2026, 23:03. Not legal advice — confirm the deadline with Clare County Council before relying on it.