PlanningRegister.ie
Observation pack · Clare County Council

Carrowntedaun tdl. , Bartra , Lahinch Co Clare V95 Y4C6

For the demolition of existing extensions of a cottage, refurbishment the existing cottage and the construction of a single storey extension, a proprietary wastewater treatment system, modifications to existing road boundaries and agricultural entrance setback and gate for site access and all associated site works

Observations close 25 Nov 2026 11 days left
5 weeks from receipt (received 21 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 15 Dec 2026

The application

Reference
2660691 · full record
Authority
Clare County Council
Type
PERMISSION
Status
NEW APPLICATION
Units
1
Floor area
208 m²
Site area
4,606 m²
Received
21 Oct 2026
Decision due
15 Dec 2026

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/ClareCC/AppFileRefDetails/2660691/0.
  2. Write your observation.Quote 2660691 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Clare County Council takes it online with the submission or at the counter.
  4. Submit before 25 Nov 2026.Online through the register above, or in writing to the Planning Department, Clare County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2660035Refused23 Mar 202610 mfor the demolition of existing extensions to cottage, refurbishment of existing cottage and construction of a two storey extension, a proprietary wastewater treatment system, modifications to existing road boundaries and agricultural entrance setback and gate for site access and all associated site works.
22467Conditional21 Sept 20221111 mto construct a dwelling house, garage, waste water treatment system, entrance from public road and all associated site works
211361Conditional23 Mar 20220 mfor a change of use from existing Stables Services Building to a dwelling house including associated modifications / upgrade works, the construction of a wastewater treatment system and associated site works

Appeals

ACP caseTypeOutcomeDecidedDistance
310491Refused24 Feb 2022338 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 21 Oct 2026 New application · observations close 25 Nov 2026
  • 21 Oct 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 3 Nov 2026, 23:01. Not legal advice — confirm the deadline with Clare County Council before relying on it.