PlanningRegister.ie
Observation pack · Clare County Council

Cloona , Dysert , Corofin Co. Clare V95 K2Y0

To retain a shed and a garage and all associated site development works

Observations close 11 Dec 2026 26 days left
5 weeks from receipt (received 6 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 9 Jan 2027

The application

Reference
2660714 · full record
Authority
Clare County Council
Type
RETENTION
Status
NEW APPLICATION
Site area
1,830 m²
Received
6 Nov 2026
Decision due
9 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/ClareCC/AppFileRefDetails/2660714/0.
  2. Write your observation.Quote 2660714 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Clare County Council takes it online with the submission or at the counter.
  4. Submit before 11 Dec 2026.Online through the register above, or in writing to the Planning Department, Clare County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Designations on or near the site within 100 m

  • Recorded monument × 1
    R125270

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
25247Refused18 Sept 2025180 mfor the construction of a single storey extension to existing out building and demolition of existing two storey derelict cottage. Works to the existing outbuilding will include the construction of a new roof and external walls and will be incorporated within the proposed extension as a replacement dwelling. The development will also consist of a new wastewater treatment system and all associated site works

What has happened on this file

  • 6 Nov 2026 New application · observations close 11 Dec 2026
  • 6 Nov 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 11 Nov 2026, 23:00. Not legal advice — confirm the deadline with Clare County Council before relying on it.