PlanningRegister.ie
Observation pack · Clare County Council

Ballynacragga , Newmarket on Fergus , Co.Clare

For the construction of a single storey dwelling, a single storey detached garage, a new entrance gateway to the public road, new on site wastewater treatment system, and all ancillary site works

Observations close 11 Dec 2026 18 days left
5 weeks from receipt (received 6 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 9 Jan 2027

The application

Reference
2660716 · full record
Authority
Clare County Council
Type
PERMISSION
Status
NEW APPLICATION
Units
1
Floor area
1 m²
Site area
2,609 m²
Received
6 Nov 2026
Decision due
9 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/ClareCC/AppFileRefDetails/2660716/0.
  2. Write your observation.Quote 2660716 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Clare County Council takes it online with the submission or at the counter.
  4. Submit before 11 Dec 2026.Online through the register above, or in writing to the Planning Department, Clare County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Designations on or near the site within 100 m

  • Recorded monument × 1
    R123849

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2660217Conditional26 May 20260 mto construct a domestic garage to the rear of the existing dwelling including all associated site development works
2560180Refused30 May 20251118 mfor a single dwelling house, garage, advanced wastewater treatment system along with ancillary site works
2460331Conditional10 Sept 2024184 mto construct a single dwelling house, garage, advanced wastewater treatment system along with ancillary site works
221095Conditional12 Oct 20230 mfor development at Newmarket-on-Fergus Wastewater Treatment Plant in the townland of Boheraroan, Newmarket-on-Fergus, Co. Clare and an associated rising main traversing the townlands of Ballyconneely, Ballynacragga, Boheraroan, Dromoland, Latoon North, Latoon South, Manusmore, Newmarket and Rathfolan, County Clare. The development will compromise proposed works within the existing Newmarket-on-Fergus Wastewater Treatment Plant, including: a. 1 No. 7.8m high storm storage tank with minimum storage capacity of 516m3, measuring approximately 11m diameter. Between 3.6m - 5.0m will be above ground level, the remainder will be buried below ground level b. New below-ground discharge pumping station with associated below-ground valve chambers and wet well c. New 4.1m high tertiary treatment system (including 2 No. tertiary filter units and flocculation tank with a volume of 8m3) d. 2 No. 2.7m high chemical storage tanks (each with a volume of 7.5m3) e. Electrical control kiosk (6.4m L x 5.2m W x 2.5m H) f. Standby generator g. Diversion of the flows from the existing final effluent pump chamber via 110m of 300mm external diameter sewer to the new discharge pumping station. The proposed development will also include: h. Construction of approximately 4.4km of 400mm diameter outfall rising main from the proposed pumping station to the proposed outfall diffuser within the River Rine i. An outfall diffuser with three diffuser heads of 225mm diameter located within the River Rine foreshore j. All ancillary works site development works including site preparation works, hardstanding, site clearance, ground levelling and site drainage as required to facilitate the development. This application is accompanied by a Natura Impact Statement (NIS).
22505Conditional10 Feb 20231412 mto construct a two-storey extension to the rear of existing building, construct new garage, connect to existing septic tank, demolish existing garage and carry out all ancillary site works
22156Conditional12 Apr 20221434 mof the following variations to the previously approved (16/106) works, namely to: a) The bungalow roof ridge line. b) The fenestration throughout, including the omission of bay windows to the side and rear. c) The bungalow front entrance. d) The front building-line of the integrated garage. e) The overall floor area which is increased. f) All associated site and internal works

Appeals

ACP caseTypeOutcomeDecidedDistance
318408Granted with conditions3 Dec 20240 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 6 Nov 2026 New application · observations close 11 Dec 2026
  • 6 Nov 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 11 Nov 2026, 23:00. Not legal advice — confirm the deadline with Clare County Council before relying on it.