Former Shannon Shamrock Hotel , Bunratty , Co. Clare

For a seven year planning permission for development comprising the regeneration of an existing brownfield site at the site of the former Shannon Shamrock Hotel at Bunratty, Co. Clare. Planning permission is sought to demolish the existing hotel, conference centre and ancillary outbuildings and to provide for the phased delivery of a mixed use development including provision of: (a) 54 no. residential units comprising 24 no. 2 bed houses and 30 no. 3 bed houses; (b) 1 no. convenience retail store of 406sqm floor area with associated external yard; (c) 2 no. retail / office units of 85sqm each; (d) creche with external play area; (e) 80 no. bedroom hotel divided across two separate 3 storey blocks including (i) entrance lobbies and associated hotel management rooms; (ii) cleaners room; and (iii) café; (f) 12 no. 2 bed duplex units for short term letting purposes; (g) a bat house; (h) a public park; (i) a new dedicated access to serve Castle Gardens Estate; and (j) all ancillary site development works including (i) car & bicycle parking; (ii) bin storage; (iii) signage; (iv) 2 no. ESB sub-stations; and (v) public lighting. The application is accompanied by a Natura Impact Statement (NIS)

Observations close 16 Dec 2026 22 days left
5 weeks from receipt (received 11 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 14 Jan 2027

The application

Reference
2660731 · full record
Authority
Clare County Council
Type
PERMISSION
Status
NEW APPLICATION
Site area
3.57 ha
Received
11 Nov 2026
Decision due
14 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/ClareCC/AppFileRefDetails/2660731/0.
  2. Write your observation.Quote 2660731 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Clare County Council takes it online with the submission or at the counter.
  4. Submit before 16 Dec 2026.Online through the register above, or in writing to the Planning Department, Clare County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
C5
Commercial, enterprise and employment
Tourism: Land zoned for tourism development shall be used for a range of structures and activities which are primarily designed to facilitate tourism developmentbunratty settlement plan20 Apr 2023 → 19 Apr 2029
G1
Open space with recreation
Open Space: It is intended that lands zoned ‘open space’ will be retained as undeveloped open space, mainly for passive open space related activities. The open space/park areas could contain active play facilities such as children’s play areas etc.bunratty settlement plan20 Apr 2023 → 19 Apr 2029
M2
Major town centre
Mixed Use: The use of land for ‘mixed use’ developments shall incl. the use of land for a range of uses, making provision, where appropriate, for primary and secondary uses e.g. commercial/retail development as the primary use with residential dev. as secondarybunratty settlement plan20 Apr 2023 → 19 Apr 2029
C5
Commercial, enterprise and employment
Tourism: Land zoned for tourism development shall be used for a range of structures and activities which are primarily designed to facilitate tourism developmentbunratty settlement plan20 Apr 2023 → 19 Apr 2029
G1
Open space with recreation
Open Space: It is intended that lands zoned ‘open space’ will be retained as undeveloped open space, mainly for passive open space related activities. The open space/park areas could contain active play facilities such as children’s play areas etc.bunratty settlement plan20 Apr 2023 → 19 Apr 2029
M2
Major town centre
Mixed Use: The use of land for ‘mixed use’ developments shall incl. the use of land for a range of uses, making provision, where appropriate, for primary and secondary uses e.g. commercial/retail development as the primary use with residential dev. as secondarybunratty settlement plan20 Apr 2023 → 19 Apr 2029

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: Clare County Council development plan zoning · fetched 25 Oct 2026, 23:00
SourceLicenceFetchedLink
Clare County Council development plan zoning—25 Oct 2026, 23:00open

Designations on or near the site within 100 m

  • NIAH-recorded building × 1
    Bunratty Castle
  • Recorded monument × 10
    Town defences · Excavation - miscellaneous · Historic town

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2560756Conditional4 Feb 202615 mto carry out - A number of internal layout modifications within the existing building, - Construct a bar / restaurant area extension with associated external terrace areas, - Remove the various existing service yard structures to the north, - Construct a new service and keg room building, service yard wall, bin compound wall and universal access WC, - Refurbish and reuse the existing Keg Room building as a Tea / Coffee / Snack / Merchandise Outlet at ground and first floor level (public road level) and to construct a storage room extension at ground floor level and a new shopfront / entrance extension, balcony and stairs at first floor level (public road level) and a new pedestrian access and crossover from the public footpath on the old Limerick / Shannon Road (L3126). - Install new signage, new connections to existing site services and all associated site works
2460618Conditional25 Sept 20250 mfor development comprising the regeneration of an existing brownfield site at the site of the former Shannon Shamrock Hotel at Bunratty, Co. Clare. A seven year planning permission is sought to demolish the existing hotel and ancillary outbuildings and to provide for the phased delivery of a mixed use development including provision of: (a) 67 no. residential units comprising 20 no. 2 bed houses and 47 no. 3 bed houses; (b) 1 no. convenience retail store of 470sqm (net) floor area; (c) 6 no. retail / office units including 4 no. units of 167sqm (net) floor area and 2 no. retail / office units of 231sqm (net) floor area intended to accommodate Class 1 & Class 2 Uses; (d) a bat house; and (e) all ancillary site development works including (i) car & bicycle parking; (ii) bin storage; (iii) signage; (iv) 2 no. ESB sub-stations; and (v) public lighting. The existing conference centre building shall be retained on site and shall form part of a future phase of development. The application is accompanied by a Natura Impact Statement
2460665Conditional24 Sept 2025241 mis sought for the proposed works: 1) removal from site and decommissioning of existing 3 No. overground fuel tanks and existing underground fuel tanks; 2) removal from site of existing washing machines facility and removal of unauthorised disused manual car wash; 3) removal of existing forecourt canopy and 4 No. fuel pumps; 4) proposed change of use from storage area to customer toilets, on the ground floor of the existing building, to include minor changes to elevations; 5) construction of new 3 No. dispenser pump islands, dispensing fuel on each side, with new canopy over; 6) installation of new underground fuel tanks, and all associated fuel pipework, off-fill points and vents and installation of new truck/HGV fuelling pump; 7) alterations to existing parking areas to provide new car parking layout, with provision of EV charging spaces and bicycle stands; 8) construction of new ESB sub-station; 9) concrete slab surfacing, asphalt surfacing and associated drainage with the provision of new Class A Petrol interceptor; 10) alterations to existing site entrances, to provide 2 No. vehicular site entrances to and from the site from public road, including alteration/extension of existing front boundary wall; 11) construction of all associated site features including public lighting and all associated ancillary site works. Planning permission for RETENTION is also sought for the existing works as constructed: 12) existing totem sign; 13) existing signage on front and side (east) elevation of amenity building; 14) existing block boundary walls along eastern and western site boundaries; 15) existing single-storey storage rooms to rear of amenity building, as constructed; 16) change of use from tea room use to residential use to provide 1 No. apartment at first floor level, inclusive of access stairs, as constructed; 17) change of use from storage areas to retail area at ground floor level of existing amenity building, as constructed; 18) existing outdoor seating areas, as constructed; 19) elevational changes to existing elevations, as constructed
2560449Conditional12 Sept 20251219 mfor amendments to the site layout as permitted (P19-939 and ABP-309278-21 Refer) comprising the reconfiguration and removal of a portion of the pedestrian footpaths as previously permitted together with all associated ancillary and incidental site works
2560385Conditional19 Aug 2025435 mfor the construction and operation of a concrete batching plant which will produce up to 50,000 m3 of ready-mix concrete annually over an area of circa 1.6 hectares within the southern portion of Bunratty Quarry, in the townland of Bunratty West, Co. Clare. The proposed concrete batching plant will include concrete plant (x 1), 100 tonne storage silos (x 4), 50,000L water tank1 (x 1), 80 tonne storage bins (x10), control cabin, admixture building, conveyor system, washout lagoons, attenuation tank, an access ramp and associated drainage infrastructure including a settlement tank. The proposed development will involve the utilisation of both virgin aggregates and recycled aggregates. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application
2560360Conditional31 Jul 2025160 mthe development which will consist of the installation of a compact modular substation and ancillary site development works; to facilitate 4 no. shared electric vehicle charging units and 8 no. charging bays; and ancillary site works within a partially reconfigured area; and the installation of signage. This site is located within the curtilage of Bunratty Castle Hotel (Protected Structure, RPS No. 077).
2560198Conditional28 Jul 202518 mof a food truck and associated seating area.
2460514Conditional20 Dec 2024221 mfor a development comprising 20 no. residential units, (6 no. detached houses, 10 no. semi-detached houses, 4 no. Duplex units), ancillary surface car parking, vehicular & pedestrian access to the proposed development via the existing residential development to the north of the site which is under construction (planning ref; 19/939), connection to public water supply; foul water drainage services including the provision of surface water attenuation and all associated site development and landscape works on lands at Bunratty West, Bunratty, Co. Clare. Works to Include alterations to the previously approved planning ref; 19/939, alterations include revised parking, road, footpath and open space where both residential schemes ajoin. The planning application is accompanied by a Natura Impact Statement (NIS)

Appeals

ACP caseTypeOutcomeDecidedDistance
500107Refused6 May 20260 m
323341Other12 Nov 20250 m
322481Invalid8 May 202560 m
309278Granted with conditions24 Jan 2022222 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 11 Nov 2026 New application · observations close 16 Dec 2026
  • 11 Nov 2026 Decision