PlanningRegister.ie
Observation pack · Cork County Council

The townlands of Coom (Hudson), Mullenaboree, Knockaunalour, Knocknacaheragh, Chimneyfield, Killeagh, Glannasack, Knockdoorty and Lackendarragh North, Co. Cork

We, Coom Green Energy Park Limited, intend to apply for permission for a Renewable Energy Development (RED III) development at this site within the townlands of Coom (Hudson), Mullenaboree, Knockaunalour, Knocknacaheragh, Chimneyfield, Killeagh, Glannasack, Knockdoorty and Lackendarragh North, Co. Cork The Renewable Energy Development (RED III) will consist of: • Installation of approximately 15.8 km of underground medium voltage (33kV) electrical and communication cabling between the western and eastern arrays of the permitted Coom Green Energy Park (ACP Ref: 04.308885) and all associated ancillary works; • Forestry felling of 13 ha to facilitate construction and operation of the Proposed Development; and • All associated infrastructure, services and site works including excavation, earthworks, soil management, drainage and sediment control to facilitate the works. • A 10-year planning permission is being sought for the construction of the Proposed Development, alongside an operational period of 30 years. The underground cabling is intended to connect the western and eastern arrays of the permitted Coom Green Energy Park (ACP Ref: 04.308885) to the proposed 110kV onsite substation at Lackendarragh North which is the subject of a separate application for consent to An Coimisiún Pleanála. This separate consent application includes the proposed onsite 110 kV substation at Lackendarragh North and associated works including 110 kV underground grid connection cabling between Lackendarragh North and the existing 110 kV Barrymore substation at Kill-Saint-Anne-North, Co. Cork. Coom Green Energy Park along with its grid connection was previously subject to EIA pursuant to planning ref. ACP Ref: 04.308885. The EIAR submitted with this application for consent assesses the entire project which includes all infrastructure associated with both applications for planning consent including the permitted Coom Green Energy Park. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) will be submitted to the Planning Authority with the Application.

Observations close 22 Oct 2026 window closed
5 weeks from receipt (received 17 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 11 Nov 2026

The five-week window has passed. Late observations are returned unread. If the council has decided, the next door is the appeal window — but under s.37 only the applicant and those who made a valid observation may appeal.

The application

Reference
26/2424 · full record
Authority
Cork County Council
Type
Permission
Status
Awaiting Recommendation
Applicant
not published by the national dataset — see the council register
Units
—
Floor area
—
Site area
38.53 ha
Received
17 Sept 2026
We first saw it
7 Oct 2026, 01:19
Decision due
11 Nov 2026
Decision
not yet decided

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://planning.agileapplications.ie/corkcoco/application-details/?ref=26/2424.
  2. Write your observation.Quote 26/2424 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Cork County Council takes it online with the submission or at the counter.
  4. Submit before 22 Oct 2026.Online through the register above, or in writing to the Planning Department, Cork County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

  • Recorded monument × 4
    Fulacht fia · Mass-rock · R113815

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
24/5715Conditional permission7 Jan 2025—0 mPermission for the construction of a new part single storey part two storey detached dwelling including a single storey detached garage, a new wastewater treatment unit and percolation area, a new site entrance, and all associated site works.
23/6382Conditional permission30 Jan 2024—47 mPermission to decommission and demolish the existing silage pit and construct new silage pit along with all associated site development works.
23/5140Conditional23 Nov 2023—304 mConstruct a dwelling house
22/4981Conditional19 Sept 2022—427 mConstruct a dwelling house.
21/6677Conditional2 Feb 2022—44 mThe continued use of an existing, temporary lattice type meteorological mast, 100m in height. The structure is fixed to ground mounted anchors by guy wires and includes associated instruments to measure local meteorological conditions. Permission is sought for a period of 5 years. The mast was previously granted temporary permission under planning reference 19/4979.

Appeals

ACP caseTypeOutcomeDecidedDistance
324274—pending7 May 20260 m
314850—Granted with conditions27 Mar 2024427 m
312886—pending28 Feb 202244 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 17 Sept 2026 New application · observations close 22 Oct 2026

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 7 Oct 2026, 01:19. Not legal advice — confirm the deadline with Cork County Council before relying on it.