PlanningRegister.ie
Observation pack · Cork County Council

Caherdaniel, Bantry, Co. Cork

Construct a two storey dwelling and domestic garage, undertake all associated site works (Change of Plan previously permitted under PL REF 22/004)

Observations close 13 Nov 2026 22 days left
5 weeks from receipt (received 9 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 3 Dec 2026

The application

Reference
26/2613 · full record
Authority
Cork County Council
Type
Permission
Status
Awaiting Recommendation
Applicant
not published by the national dataset — see the council register
Units
—
Floor area
—
Site area
1,981 m²
Received
9 Oct 2026
We first saw it
21 Oct 2026, 02:10
Decision due
3 Dec 2026
Decision
not yet decided

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://planning.agileapplications.ie/corkcoco/application-details/?ref=26/2613.
  2. Write your observation.Quote 26/2613 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Cork County Council takes it online with the submission or at the counter.
  4. Submit before 13 Nov 2026.Online through the register above, or in writing to the Planning Department, Cork County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
G3
High amenity
Greenbelt1: Discourage strongly new individual housing from being located within the greenbelts around the Main Towns.cork county development plan 20226 Jun 2022 → 5 Jun 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: Cork County Council development plan zoning · fetched 27 Sept 2026, 19:37
SourceLicenceFetchedLink
Cork County Council development plan zoning—27 Sept 2026, 19:37open

Designations on or near the site

Nothing designated within 100 m of the site.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
26/1786Grant with conditions13 Aug 2026—468 mPermission to install a replacement wastewater treatment system, in lieu of the old septic tank system which will be infilled and decommissioned
25/401Refused10 Sept 2025—151 mConstruction of a community dwellinghouse and all associated site works
23/628Conditional28 Jun 2024—485 mConstruct a straw bedded sheep house with hay and straw storage area, seepage holding tank, site entrance, internal access road and carry out all associated site works
23/432Conditional28 Oct 2023—8 mPermission is being sought for the change of use of part of existing storage shed / garage to self-contained habitable accommodation ancillary in use to the main dwelling house including the following: (i) retention of external fenestration changes, (ii) permission for installation of new patio doors, (iii) decommissioning of existing septic tank system and installation of wastewater pumping station to discharge to public sewer and (iv) all associated site works
23/248Refused27 Jun 2023—485 mConstruct a sheep house with hay and straw storage area, site entrance, internal access road and carry out all associated site works
23/120Refused27 Apr 2023—8 mPermission for: (a) construction of new detached domestic garage (b) change of use of an existing storage shed / garage to habitable use, as a granny flat ancillary to the main dwelling house including the following: (i) retention of external fenestration changes, (ii) permission for new fenestration changes including installation of new window, patio doors and rooflight, (iii) decommissioning of existing septic tank system and installation of wastewater pumping station to discharge to public sewer and (iv) all associated site works
22/241Conditional23 Jun 2022—32 mConstruction of a dwelling house and associated site works
22/17Conditional22 Jun 2022—102 mPermission for retention for the following:- (a) Fenestration changes to windows, doors and roof lights and alterations to stone external cladding of said dwelling. (b) Change of use of attached garage within dwelling for use as bedroom/gym. (c) Single storey utility addition to rear south elevation of said dwelling. Permission also sought for the following:- (d) Sunroom extension to said dwelling. (e) Detached ancillary dwelling unit and for all associated site works

Appeals

No appeals within 500 m in the last 5 years.

What has happened on this file

  • 9 Oct 2026 New application · observations close 13 Nov 2026

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 21 Oct 2026, 02:10. Not legal advice — confirm the deadline with Cork County Council before relying on it.