PlanningRegister.ie
Observation pack · Cork County Council

Mardyke, Barry's Road, Schull, Co. Cork, P81P031

Retention of mobile home for a period of 3 years

Observations close 19 Nov 2026 5 days left
5 weeks from receipt (received 15 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 9 Dec 2026

The application

Reference
26/2666 · full record
Authority
Cork County Council
Type
Permission for Retention
Status
Awaiting Recommendation
Site area
2,436 m²
Received
15 Oct 2026
Decision due
9 Dec 2026

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://planning.agileapplications.ie/corkcoco/application-details/?ref=26/2666.
  2. Write your observation.Quote 26/2666 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Cork County Council takes it online with the submission or at the counter.
  4. Submit before 19 Nov 2026.Online through the register above, or in writing to the Planning Department, Cork County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
G3
High amenity
Greenbelt1: Discourage strongly new individual housing from being located within the greenbelts around the Main Towns.cork county development plan 20226 Jun 2022 → 5 Jun 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: Cork County Council development plan zoning · fetched 27 Sept 2026, 19:37
SourceLicenceFetchedLink
Cork County Council development plan zoning—27 Sept 2026, 19:37open

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedDistanceDescription
26/0749Grant with conditions13 May 2026328 mPermission for Retention of a dwellinghouse & detached garage as constructed
25/6433Grant with conditions2 Mar 2026210 mProposed extensions, alterations and renovations to an existing detached dwelling house, the construction of a detached garage, the demolition of ancillary structures on site and all associated site works
25/6671Unconditional permission6 Feb 2026402 mConstruction of 2 no. Two storey (3 Bed) Dwellings, 4 No. car parking spaces and all associated site works (previous permissions 05/1839, 08/1110, 13/426).
25/220Conditional permission24 Sept 2025308 mConstruction of a proposed new detached dwelling house and all associated site works
25/109Conditional permission9 Sept 2025487 mPermission for the demolition of existing bin store and the construction of 4 no. residential units and all ancillary site development works including landscaping, parking and new proposed bin store
24/225Conditional permission13 May 2025265 mPermission for the construction of 57 no. residential units (comprising a mix of 3, 4 and 5 bed dwelling houses and 1 and 2 bed duplex/apartment units) and all associated ancillary development works including, vehicular and pedestrian access on to Colla Road, via Chestnut Grove, a pedestrian connection to Copper Point residential estate, footpaths, lighting, parking (vehicular and bicycle), drainage, landscaping, amenity areas, bin and bike storage, ESB Substation and undergrounding of overhead electricity power lines
24/697Conditional permission3 Apr 2025342 mDemolish the existing 1.5 storey dwelling and to construct new 1.5 storey dwelling, new vehicular site entrance and new single-storey garden shed - (change of design to dwelling and site entrance as previously permitted under planning reference 22/598)
24/390Conditional5 Sept 2024237 mPermission for alterations and extensions to an existing dwellinghouse, to consist of (a) demolition of an attached garage, boiler house and chimney stack (b) alterations to internal layout, external fenestration and roof (c) construction of extensions (d) all associated site development works, to include the demolition of a detached greenhouse

Appeals

ACP caseTypeOutcomeDecidedDistance
323719Granted with conditions3 Feb 2026487 m
322693Granted with conditions6 Oct 2025265 m
314251Withdrawn30 Aug 2022342 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 15 Oct 2026 New application · observations close 19 Nov 2026

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 28 Oct 2026, 01:34. Not legal advice — confirm the deadline with Cork County Council before relying on it.