Coorycommane,, Coomhola,, Bantry, Co. Cork

Construction of dwelling house and all associated site works

Observations close 27 Nov 2026 12 days left
5 weeks from receipt (received 23 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 17 Dec 2026

The application

Reference
26/2756 · full record
Authority
Cork County Council
Type
Permission
Status
Awaiting Recommendation
Site area
4,617 m²
Received
23 Oct 2026
Decision due
17 Dec 2026

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://planning.agileapplications.ie/corkcoco/application-details/?ref=26/2756.
  2. Write your observation.Quote 26/2756 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Cork County Council takes it online with the submission or at the counter.
  4. Submit before 27 Nov 2026.Online through the register above, or in writing to the Planning Department, Cork County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedDistanceDescription
26/2325Grant with conditions2 Nov 202646 mPermission for installation of replacement wastewater treatment system to service existing dwelling house and for decommissioning of existing system
26/0862Grant with conditions27 May 2026251 mTo install sewerage treatment system to serve existing dwelling and de-commission existing septic tank
24/362Conditional27 Aug 2024349 mPermission sought for retention of domestic site works and access road and for permission for change of house design (previously granted under Pla. Ref. No. 20/291). Permission also sought for detached domestic store and for all associated site works.
23/617Conditional2 Feb 2024290 mPermission sought for retention of dwelling house and site boundaries (previously granted under Pl. Ref. No. 20/290) Permission also sought for retention of detached domestic store, location of waste water treatment system and for all associated site works
23/603Conditional23 Jan 20240 mPermission for construction of dwelling house, detached domestic garage and all associated site works
23/57Conditional29 May 2023304 mPermission for the following: (i) change of plan of proposed dwelling house and change of site layout (as previously approved under planning ref: 22/00258), and (ii) permission for construction of detached domestic garage and for associated site works
22/258Conditional3 Jan 2023304 mConstruction of dwelling house, installation of wastewater treatment system and associated works
22/257Conditional3 Jan 2023358 mConstruction of dwelling house, installation of wastewater treatment system and associated works

What has happened on this file

  • 23 Oct 2026 New application · observations close 27 Nov 2026