PlanningRegister.ie
Observation pack · Cork County Council

Druids Knoll, Ballindeasig Td., Nohoval , Co.Cork

1. Permission for retention of as a constructed one and a half storey storage outbuilding that differs from the one granted under planning application 13/5384 to also include elevational changes; 2. Permission to construct a one and a half storey dwelling house to include a ground floor granny flat, install a wastewater treatment system and tertiary sandcel (percolation area) and all associated site works

Observations close 1 Dec 2026 17 days left
5 weeks from receipt (received 27 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 21 Dec 2026

The application

Reference
26/2772 · full record
Authority
Cork County Council
Type
Permission
Status
Awaiting Recommendation
Site area
2,199 m²
Received
27 Oct 2026
Decision due
21 Dec 2026

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://planning.agileapplications.ie/corkcoco/application-details/?ref=26/2772.
  2. Write your observation.Quote 26/2772 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Cork County Council takes it online with the submission or at the counter.
  4. Submit before 1 Dec 2026.Online through the register above, or in writing to the Planning Department, Cork County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Designations on or near the site within 100 m

  • Recorded monument × 1
    R108303

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedDistanceDescription
23/5041Refused17 Oct 2023464 mPlanning permission for the construction of a dwelling, site entrance and all associated site works including a wastewater treatment system.
22/6493Refused11 Jan 2023464 mConstruction of a dwelling, garage, site entrance, and all associated site works including a waste water treatment system.

Appeals

ACP caseTypeOutcomeDecidedDistance
318437Refused10 Sept 2024464 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 27 Oct 2026 New application · observations close 1 Dec 2026

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 10 Nov 2026, 23:01. Not legal advice — confirm the deadline with Cork County Council before relying on it.