Annabella TD, Mallow, Co. Cork.

Permission for retention of existing ''as built'' dwelling and all associated site works and services and for permission to remove existing septic tank serving existing dwelling and to replace same with a new secondary wastewater treatment unit and tertiary filter and all associated works and services

Observations close 7 Dec 2026 21 days left
5 weeks from receipt (received 2 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 5 Jan 2027

The application

Reference
26/2826 · full record
Authority
Cork County Council
Type
Permission for Retention
Status
Awaiting Validation SRO
Site area
2,054 m²
Received
2 Nov 2026
Decision due
5 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://planning.agileapplications.ie/corkcoco/application-details/?ref=26/2826.
  2. Write your observation.Quote 26/2826 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Cork County Council takes it online with the submission or at the counter.
  4. Submit before 7 Dec 2026.Online through the register above, or in writing to the Planning Department, Cork County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
G3
High amenity
Green Infrastructure includes 3 subcategories - Green Recreational (GR), Green Conservation (GC) and Green Active (GA)cork county development plan 20226 Jun 2022 → 5 Jun 2028
R2
Existing residential
Existing Residential/Mixed Residential and Other Uses: The scale of new residential and mixed residential developments within the Existing Residential/Mixed Residential and Other Uses within the settlement network should normally respect the pattern and grain of existing urban development in the surroundingcork county development plan 20226 Jun 2022 → 5 Jun 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: Cork County Council development plan zoning · fetched 27 Sept 2026, 19:37
SourceLicenceFetchedLink
Cork County Council development plan zoning—27 Sept 2026, 19:37open

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedDistanceDescription
26/1033Grant with conditions16 Jun 202673 mPermission to retain 1) Alterations to dwelling granted under planning Reference No. 18/7100, including increased floor area, addition of windows and modifications to window and door sizes and locations, altered ridge height, and change of external finish from natural stone to smooth plaster on three elevations, 2) Retaining walls constructed along the northern, eastern and western site boundaries, 3) Garage for domestic use and 4) Relocation of vehicular entrance and all associated site works.
26/0160Unconditional permission20 Mar 2026148 mPermission to construct 2 no. detached split level dwellings, development works to existing access passage including entrances and all necessary ancillary works. Extension of Duration to Permission granted under Planning Ref. No. 20/5886
25/5402Grant with conditions11 Mar 202624 mPermission to construct a new dwelling house with domestic garage, entrance, wastewater treatment unit with percolation area and all associated site and ancillary work
25/6296Refused12 Feb 2026148 mPermission to construct 2 no. detached split level dwellings, development works to existing access passage including entrances and all necessary ancillary works, Extension of Duration to Permission granted under planning ref. No. 20/5886.
25/6175Grant with conditions5 Dec 2025261 mPermission for Retention of the existing single storey extension to the side of the existing dwelling house with alterations and all associated and ancillary works.
25/5124Conditional permission4 Nov 2025320 mPermission for large-scale residential development (LRD), the construction of a residential development of 102 no. residential units comprising of 36 no. dwelling houses and 66 no. apartment/duplex/maisonette units, a two storey creche facility and all ancillary site development works. The proposed 36 no. dwelling houses will all be 3 bedroom mid and end terrace units. The proposed 66 no. apartment/duplex/maisonette units consist of 17 no. 3 bedroom units, 33 no. 2 bedroom units and 16 no. 1 bedroom units. 32 no. of the proposed apartment/duplex/maisonette units will be accommodated in 8 no. 2 storey buildings in southern and central areas of the site, with the remaining 34 no. apartment/duplex/maisonette units being accommodated in a 1-3 storey apartment building to the north of the site. The proposed development facilitates pedestrian and cycle connections to the existing Woodview Drive residential development to the east and the residential development to the west permitted by An Bord Pleanála reference 312640-22, which is currently under construction. Access to the proposed development will be provided via the internal road network of the Annabella Park residential development. The proposed development provides for upgrades to the existing internal road network and public realm of the Annabella Park residential development including new footpaths, public lighting and traffic calming measures. Other ancillary site development works include landscape and amenity areas, public open spaces, servicing and drainage proposals (including SuDs measures), bicycling parking, bin storage facilities and an ESB substation. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application. LRD Website: www.AnnabellaLRD.ie
25/4364Conditional24 Apr 2025406 mPermission for Retention of the extensions to the front, rear and side of the existing dwelling, (2) Permission for the decommissioning of the existing septic tanks, (3) permission for the installation of a secondary treatment system and soil polishing filter and all associated site works.
24/6432Conditional16 Apr 2025335 mPermission for Mallow Water infrastructure upgrades, to include:- upgrades to the Kennel Hill Service Reservoir, including the erection of 2 no. above ground kiosks, 1 no. below ground chamber, new hardstanding, relocation of the existing kiosk, decommissioning and demolition of the existing reservoir, and the demolition of the existing single storey control building, and an upgrade of 410 metres of existing watermain from an existing valve arrangement located south-west of the Annabella Roundabout, west along Navigation Road (N72) and beneath Annabella Bridge (a Protected Structure RPS 02431) to the proposed new kiosk at Kennel Hill Service Reservoir on Kennel Hill. The proposed development will also consist of works within the curtilage of a Protected Structure and all site development and landscaping works.

Appeals

ACP caseTypeOutcomeDecidedDistance
323904Granted with conditions27 Mar 2026320 m
316136Refused29 Feb 202460 m
317016Other17 Oct 2023313 m
317015Other12 Oct 2023424 m
312640Granted with conditions27 May 2022295 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 2 Nov 2026 New application · observations close 7 Dec 2026

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 10 Nov 2026, 23:01. Not legal advice — confirm the deadline with Cork County Council before relying on it.