Application for permission of: a) a two storey extension to the rear and side; b) a roof terrace at first floor level to the side; c) two roof windows to the front of existing house, with associated sundry works to an end-terraced single storey cottage, at 8 Strand Terrace, Milltown, Dublin 6, D06 W950.

Observations close 26 Nov 2026 20 days left
5 weeks from receipt (received 22 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20

The application

Reference
WEB3598/26 · full record
Authority
Dublin City Council
Type
Permission
Status
Registered Application
Applicant
not published by the national dataset — see the council register
Units
—
Floor area
—
Site area
—
Received
22 Oct 2026
We first saw it
30 Oct 2026, 23:08
Decision due
—
Decision
not yet decided

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.No register URL is recorded for this reference; search the Dublin City Council planning register for WEB3598/26.
  2. Write your observation.Quote WEB3598/26 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Dublin City Council takes it online with the submission or at the counter.
  4. Submit before 26 Nov 2026.Online through the register above, or in writing to the Planning Department, Dublin City Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
C2.1
Economic development and employment
EE: To provide for enterprise and employment related usessouth dublin county development plan 2022 20288 Mar 2022 → 8 Mar 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: South Dublin County Council development plan zoning · fetched 11 Sept 2026, 23:18
SourceLicenceFetchedLink
South Dublin County Council development plan zoning—11 Sept 2026, 23:18open

Designations on or near the site

  • Radon risk area × 1
    About 1 in 10 homes in this area is likely to have high radon levels

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
WEB3007/26Grant permission7 Oct 2026—0 mWe, O'Flynn Construction (Milltown) Limited, intend to apply for planning permission for amendments to the development permitted under An Coimisiún Pleanála Ref. ABP313048-22 and Dublin City Council Reg. Ref. 4115/21, as amended by Dublin City Council Reg. Ref. WEB2775/24, on lands at Nos. 9-14 and 11C Milltown Road, Milltown, Dublin 6. The application site comprises the former Murphy & Gunn site (currently Autovision) and the former St. Joseph's Junior Education Centre site. The proposed development consists of amendments to Block A of the permitted development and comprises the following: • Change of use of 147.7 sq.m of the permitted ground floor residents' amenity floorspace within Block A to provide 4 no. studio apartments. • Reconfiguration of 1 no. permitted ground floor 2-bedroom apartment to provide 1 no. 1-bedroom apartment. • The provision of an additional 4 no. cycle parking spaces at basement level, increasing the number of cycle spaces from 175 to 179. • Associated internal reconfiguration of ground floor and minor amendments to the ground floor elevations, including revised glazing arrangements; and • All associated site development works. The proposed amendments will increase the total number of permitted residential units from 74 no. to 78 no. apartments. The development, as amended, will result in a revised unit mix of 4 no. studio apartments, 36 no. 1-bedroom apartments and 38 no. 2-bedroom apartments.
WEB2951/26Application declared invalid11 Aug 2026—0 mWe, O'Flynn Construction (Milltown) Limited, intend to apply for planning permission for amendments to the development permitted under An Coimisiún Pleanála Ref. ABP313048-22 and Dublin City Council Reg. Ref. 4115/21, as amended by Dublin City Council Reg. Ref. WEB2775/24, on lands at Nos. 9–14 and 11C Milltown Road, Milltown, Dublin 6. The application site comprises the former Murphy & Gunn site (currently Autovision) and the former St. Joseph's Junior Education Centre site. The proposed development consists of amendments to Block A of the permitted development and comprises the following:• Change of use of 147.7 sq.m of the permitted ground floor residents' amenity floorspace within Block A to provide 4 no. studio apartments. • Reconfiguration of 1 no. permitted ground floor 2-bedroom apartment to provide 1 no. 1-bedroom apartment. • The provision of an additional 4 no. cycle parking spaces at basement level, increasing the number of cycle spaces from 175 to 179. • Associated internal reconfiguration of ground floor and minor amendments to the ground floor elevations, including revised glazing arrangements; and • All associated site development works. The proposed amendments will increase the total number of permitted residential units from 74 no. to 78 no. apartments. The development, as amended, will result in a revised unit mix of 4 no. studio apartments, 36 no. 1-bedroom apartments and 38 no. 2-bedroom apartments.
SD20A/0324/EPGrant extension of duration of permission23 Jun 2026—214 mDemolition of existing two storey dwelling of 'Bulmer' and associated outbuildings and demolition of the existing single storey house of 'Little Acre' and its associated garage and other buildings; demolition of single storey stable building on the overall site; construction of 2 two storey Information Communication Technology (ICT) facilities each with three storey plant levels and associated ancillary development which will have a gross floor area of 30,518sq.m on an overall site of 8.2 hectares; 1 two storey ICT facility (building A) will be located to the south-east of the site and will have a gross floor area of 15,196sq.m including 18 emergency generators located at ground and first floor level within a compound to the north-eastern side of the ICT facility with associated flues that will be 25m in height and will be grouped in four groups of four and 1 group of two flues (18 flues overall); 1 two storey ICT facility (building B) will be located to the north-west of Building A and centrally within the overall site and will have a gross floor area of 15,196sq.m including 18 emergency generators located at ground and first floor level within a compound to the north-eastern side of the ICT facility with associated flues that will be 25m in height and will be grouped in four groups of four and 1 group of two flues (18 flues overall); each of the two ICT facilities will include data storage rooms, associated electrical and mechanical plant rooms, loading bays, maintenance and storage spaces, office administration areas; 2 pump rooms of 25sq.m each (4 overall - 100sq.m) plus water storage tanks and plant as well as a separate house generator that will provide emergency power to the admin and ancillary spaces; each generator will also include a diesel belly tank with a single refuelling area to serve the proposed emergency generators; 1 temporary and single storey substation (26sq.m); ancillary site development works including attenuation ponds and the installation and connection to the underground foul and storm water drainage network and installation of utility ducts and cables; other ancillary site development works will include hard and soft landscaping throughout the site, lighting, fencing, signage, central services road, security gate, sprinkler tank house and 80 car parking spaces and 17 sheltered bicycle parking spaces; the development will be enclosed with landscaping to all frontages including a wetland to the south-east and will be accessed from the Peamount Road (R120) located within the townland of Milltown on lands that contain the 2 residential properties of 'Little Acre' and 'Bulmer' as well as agricultural lands and buildings which are located to the north of the Peamount Road and the lands to the north and within the overall site are subject to a concurrent application for a Power Generation Facility under Reg. SD20A/0058; An Environmental Impact Assessment Report (EIAR) is included with the application.
SD25A/0247Refuse permission1 Dec 2025—218 mA new part single/part two-storey dwelling, with new vehicular access off Peamount Lane, a proprietary wastewater treatment system, and all associated site and infrastructural works.
SD25A/0135WGrant permission20 Nov 2025—322 mThe development will consist of the omission of a permitted above ground installation (AGI) compound under Reg. Ref.: SD20A/0058, the provision of an AGI at an alternate location within the site, and the provision of a Pressure Reduction Metering System (PRMS) and a foul pumping station, along with road upgrades to the public road (R120 Peamount Road), and provision of a foul sewer connection from the site to the northeast, via Peamount Road and Old Nangor Road. The relocated AGI, PRMS compound, and foul pumping station will be located in the southeastern corner of the site. It is proposed to demolish an existing two storey vacant house (with a gross floor area of 235 sq.m.) to provide for the AGI, PRMS compound, and foul pumping station. The relocated Gas AGI and the PRMS will be located within fenced compounds and will comprise of the following buildings and gas-related infrastructure: - 2 no. AGI buildings comprising AGI Building 1 with a total area of c.18 sq.m and overall height of c. 3.4m and AGI Building 2 with a total area of c. 8 sqm and overall height of c. 3.1m; - A Boiler House Kiosk with a total area of c. 12 sq.m and overall height c. 3.5m and boiler flues with a total height c. 5.4m; - A new E&I Kiosk with a total area of c. 12 sq.m and overall height of c. 2.7m; - A new Control Room with a total area of c. 12 sq.m and overall height of c. 3m; - A new Skid House with a total area of c. 123 sq.m and overall height of c. 3.3m; - The compounds will also accommodate associated valves and pipework. A new foul water pumping station with associated chambers, meters and a 24-hour storage tank will be provided to the east of the AGI and PRMS compounds. The proposed developmbent includes all associated and ancillary works including site lighting, boundary treatments, landscaping, drainage and infrastructure. The proposed development is located within a site subject to an application for an EPA Industrial Emissions (IE) Directive license.
SD23A/0331Withdraw the application24 Jun 2024—250 m10-year permission for development for a Filling & Packaging Facility for medicines, located at Grange Castle Business Park West, Milltown and Loughtown Upper Townlands, New Nangor Road, Clondalkin, Dublin 22 as described herein. The proposed development will consist of buildings with a total area of approximately 147,192 square metres and infrastructure required to support the proposed development including: (a) 3 no. 3-level filling buildings, each sized approximately 10,637 square metres and approximately 22.1 metres high, with roof-mounted plant and equipment and solar panels. (b) A 2-level warehouse building with high-bay automatic storage and retrieval system (ASRS) area, sized approximately 18,655 square metres and approximately 33.7 meters high, with roof-mounted plant and equipment and solar panels. (c) 2 no. 3-level assembly and packaging buildings, one sized approximately 24,975 square metres and approximately 17.9 meters high, and one sized approximately 24,175 square metres and approximately 17.9 meters high both with roof-mounted plant and equipment and solar panels. (d) A 5-level administration building sized approximately 20,613 square metres and approximately 28.5 metres high with roof-mounted plant and equipment and solar panels. (e) A 4-level laboratory building sized approximately 4,733 square metres and approximately 21.8 metres high and roof-mounted plant and equipment and solar panels. (f) A 2-level pedestrian and materials spine building sized approximately 10,815 square metres and approximately 15.5 metres high, with roof mounted plant and equipment including louvred screen. (g) A 2-level Central Utilities Building (CUB) building sized approximately 9,312 square metres and approximately 17.7 metres, with roof-mounted plant and equipment including louvred screen. (h) A 2-level pedestrian and materials link area sized approximately 502 square metres and approximately 15.5 metres high with roof-mounted plant and equipment. (i) A single storey bicycle shelter and cyclist shower/changing facility building located to the west of the administration building, sized approximately 440 square metres and approximately 4 metres high. (j) A single storey fire water pumphouse sized approximately 75 square metres and approximately 6 metres high. (k) A single storey water pumphouse sized approximately 200 square metres and approximately 6 metres high. (l) A chemical stores sized approximately 120 metres and approximately 6 metres high located in the yard adjacent to the proposed Central Utilities Building (CUB). (m) A proposed car park including approximately 551 car parking spaces, including accessible car parking spaces, electric vehicle charging, motorcycle parking, dedicated car-pooling spaces, all accessed from the internal Grange Castle West Business Park roads. (n) 2 no. single-storey security buildings one sized approximately 30 square metres and approximately 3.7 metres high and one sized approximately 91 square metres and approximately 3.7 metres high. (o) The proposed site infrastructure includes cooling towers/heat exchangers, a tank farm, pipe-bridges, surface water harvest tanks, docks and yard areas, including associated items of plant and equipment, an electric vehicle charging and solar panel substation to service photovoltaic panels over new car parking spaces sized approximately 50 square metres and approximately 6 metres high, 2 no. smart shelters to accommodate plant and equipment, associated works for re-routing of the existing ESB overhead wires which traverse the site to underground cables within the site, storage structures and modular control units and underground pumping facilities and internal roads and paths, fencing and site lighting. (p) the development includes an additional heavy goods vehicle entrance from the internal Grange Castle West Business Park road to the northeast corner of the proposed campus, including modifications to the existing road and footpaths. (q) Proposed new landscaping includes new landscaped and plated areas, landscaped berms, ponds, swales and surface water attenuation features, perimeter security fencing and gates. (r) Proposed new signage based at ground level and on the building facades on the proposed new buildings. (s) The works include temporary contractor compounds including temporary cabins, temporary car parking and the temporary use of existing site entrances during construction activities. (t) Proposed new surface water management infrastructure of the site, consisting of underground and surface attenuation systems, rainwater harvest cisterns and distribution pipework and the diversion and modifications to the existing public foul sewer pipelines, including the relocation of an existing macerator. (u) The re-routing of the existing watercourse to the northeast corner of the site to include additional biodiversity features. (v) The construction of a new 38kVA electrical substation compound including 3 no. buildings, one sized approximately 135 square metres and approximately 6 metres high, one sized approximately 310 square metres and approximately 6 metres high and one sized approximately 50 square metres and approximately 6 metres high and a compound to accommodate 5 no. electrical generators and associated fuel tanks and electrical transformers with dedicated vehicular access from the public road to the northwest corner of the site (w) all associated site works including sustainability features described herein. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) accompany this planning application.
SD23B/0416Grant permission15 Mar 2024—179 mRenovation of existing detached dwelling comprising of single storey peripheral extension. Removal of existing roof structure and remodel of internal layout, comprising of 2 no. bedrooms at first floor level and living room, office, WC and utility room at ground floor level. Construction of new one and two storey extension to the side of existing dwelling, comprising of 2 no bedrooms and en-suite at first floor and open plan kitchen, living and dining space and plant room at ground floor level. Upgrading of effluent treatment system and all associated ground works
SD23A/0148Grant permission22 Aug 2023—484 mPlanning permission is being sought by Peamount Healthcare CLG for part change of use from ancillary staff accommodation to laundry, and material alterations to include; (i) new door - front elevation (ii) new double doors - side elevation (iii) new double doors - rear elevation (iv) internal alterations and all associated site works at the Avenue Building, Peamount Hospital Campus, Newcastle, Country Dublin

Appeals

ACP caseTypeOutcomeDecidedDistance
500550Planning AppealRefused8 Apr 2026218 m
323980—pending19 Dec 2025388 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 22 Oct 2026 New application · observations close 26 Nov 2026