Site located along Silloge Road and Balbutcher Lane, Ballymun,, Dublin 11, (the former Ballymun shopping centre site).

We, The Land Development Agency, intend to apply for planning permission for a Large-scale Residential Development (LRD) at a site located along Silloge Road and Balbutcher Lane, Ballymun, Dublin 11 (the former Ballymun Shopping Centre site). The subject site has an overall area of c. 2.1 hectares. The proposed development will consist of: • Site clearance works including the removal of a portion of the existing car park on site, the felling of trees on site and removal of existing bus bay (not currently in use) along Silloge Road; • The construction of three blocks ranging in height between 6-12 storeys, comprising 564 no. apartment units (91 no. studios, 190 no. 1 bedroom units and 283 no. 2 bedroom units), a creche facility (519 sqm) and 4 no. arts/cultural/community spaces (861 sqm); o Block 1 is 10 - 12 storeys and includes 253 no. apartments (38 no. studios, 93 no. 1 beds and 122 no. 2 beds); o Block 2 is 9 storeys and includes 90 no. apartments (17 no. studios, 40 no. 1 beds and 33 no. 2 beds); o Block 3 is 6 - 8 storeys and includes 221 no. apartments (36 no. studios, 57 no. 1 beds and 128 no. 2 beds); • Provision of a childcare facility of c. 519 sqm at ground floor level of Block 1, with associated external play area; • Provision of 4 no. arts/cultural/community spaces at ground floor level of Block 1 (Space 2: 210 sqm and Space 3; 332 sqm), Block 2 (Space 4: 145 sqm) and Block 3 (Space 1: 174 sqm); • The provision of balconies on elevations to serve the proposed residential units; • An external landscaped communal area (3,467 sqm) including play area within the proposed development; • A public open space (1,991 sqm) with a play area to the north east of the site; • Provision of a podium level to provide for car parking to serve the development; • The provision of 175 no. car parking spaces (including 89 no. podium spaces, 76 no. on street spaces and 10 no. on street club share spaces) which includes the reconfiguration of the existing on-street perimeter car parking;• Provision of 7 no. motorcycle spaces, and 1,130 no. bicycle parking spaces to serve the residential development (848 no. long stay and 282 no. short stay spaces) and 32 no. non-residential bicycle parking spaces (9 no. long stay spaces and 23 no. visitor spaces) at ground floor level throughout the site;• A new mobility hub which provides for 5 no. e-bike parking spaces and a pump station;• The provision of a new vehicle access point off Silloge Road to the southwest of the site and a new internal access road within the site;• The provision of 2 no. service bays to serve the development; • Upgrades to the junction between Balbutcher Lane and Silloge Road; • Relocation of the existing signal-controlled pedestrian crossing on Silloge Road and its upgrade to a toucan crossing; • The proposed development also includes all associated public realm and road upgrades, pedestrian crossings, cycle infrastructure, landscape works, boundary treatments, plant, substations, bin store areas and associated site development works. An Environmental Impact Assessment Report has been prepared in respect of the proposed development and has been submitted with the LRD application. A dedicated website has been set up for the LRD application which can be viewed at: www.sillogeroadlrd.ie…

Observations close 4 Dec 2026 8 days left
5 weeks from receipt (received 30 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20

The application

Reference
WEBLRD9013/26-S3 · full record
Authority
Dublin City Council
Type
Large Residential Development-3
Status
Registered Application
Applicant
The Land Development Agency
Received
30 Oct 2026

The council’s feed cuts this description short. The full text and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://planning.agileapplications.ie/dublincity/application-details/?ref=WEBLRD9013%2F26-S3.
  2. Write your observation.Quote WEBLRD9013/26-S3 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Dublin City Council takes it online with the submission or at the counter.
  4. Submit before 4 Dec 2026.Online through the register above, or in writing to the Planning Department, Dublin City Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
HT - High Technology: Facilitate opportunities for high technology, high technology and advanced manufacturing, major office and research and development based employment within high quality, highly accessible, campus style settings. The HT zoning is aimed at providing a location for high end, high quality, value added businesses and corporate headquarters. An emphasis on exemplar sustainable design and aesthetic quality will be promoted to enhance corporate image and identity.Fingal County Council development plan
C3
High technology
HT - High Technology: Provide for office, research and development and high technology/high technology manufacturing type employment in a high quality built and landscaped environmentthe fingal development plan 2023 20295 Apr 2023 → 5 Apr 2029

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: Fingal County Council development plan zoning · fetched 11 Sept 2026, 15:18
SourceLicenceFetchedLink
Fingal County Council development plan zoning—11 Sept 2026, 15:18open

Designations on or near the site within 100 m

  • Radon risk area × 1
    About 1 in 20 homes in this area is likely to have high radon levels

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedDistanceDescription
F26A/0453EGrant permission23 Jul 2026121 mPermission for development which will consist of the construction of a medium voltage (MV) underground cable (UGC), c.3.7 km in length, between the existing Poppintree 110kV substation on a site to the south of St. Margaret's Road (R104) in the townland of Ballymun, Co. Dublin and a proposed single-storey 20kV substation on a site to the south of the Old Airport Road (L2015) in the townland of Ballystraun, Co. Dublin. The proposed UGC will be principally located underneath public roads (R104, M50, and Naul Road (R108)) in the townlands of Ballymun and Balcurris, Co. Dublin (c. 2.3 km in length), with the remainder, c. 1.4km in length, located in the townlands of Ballymun, Coultry and Ballystraun, Co. Dublin. The proposed UGC will require Horizontal Directional Drilling (HDD) under the M50 and under the Turnapin Stream. The proposed development will also consist of 2 no. single-storey 20kV substations, including 1 no. 20kV substation (Substation 1) on a site to the south of the R104 in the townland of Balcurris, Co. Dublin, and 1 no. 20kV substation (Substation 2) on a site to the south of the Old Airport Road (L2015) in the townland of Ballystraun, Co. Dublin, and all site development and landscaping works, including a construction compound, and a HDD work area. The UGC route will consist of a trench containing 4 no. 125mm diameter ducts as far as Substation 1 where 2 no. 125mm diameter ducts will terminate, and the remaining 2 no. 125mm diameter ducts will continue to their termination at Substation 2. The proposed development will serve the construction phase of MetroLink. On 30 September 2025 An Coimisiún Pleanála granted a Railway Order for MetroLink (the 'RO') pursuant to Section 43 (2) of the Transport (Railway Infrastructure) Act 2001 (as amended) (the '2001 Act'). On 12 January 2026, the RO became operative pursuant to Section 43 (4) of the 2001 Act. Following completion of the MetroLink tunnelling works, the proposed UGC located underneath public roads
F23A/0721Grant permission30 Jan 2024157 mWe, Frylite (Dublin) Ltd, intend to apply for permission for development/continuation of use at 'Frylite', Ballystruan Lane, Swords, Co. Dublin K67 K5X0. (The site was known and referred to in previous planning applications as the ABP Meat Processing Plant, St. Anne's Cloghran, Ballymun, Co. Dublin). The development will consist of temporary permission (5 years) for the the continuation of development granted temporary planning permission under P.A. Ref. F19A/0095. As per planning permission F19A/0095 the development consists of the continuation of the temporary change of use of part of the ABP meat processing plant from meat processing to a waste transfer and processing facility (non-hazardous wastes) providing for / incorporating: (a) The collection, processing, storage and bulking up of used and fresh cooking oil; (b) A waste transfer facility for food waste;(c) the washing of used cooking oil containers (d) a dissolved air floatation tank, (e) continued use of a portacabin office accommodation (permitted under P.A. Ref. F16A/0387), (f) continued use of part of the building for collection, storage and bulking up of used cooking oil, (g) use of 6no. existing silos for storage of fresh cooking oil and use of existing 1 no. silo for storage of used cooking oil, (h) 6 no. silos for storage of used cooking oil and, (i) all related site development works. A waste facility permit is required from Fingal County Council for this proposed development.
F23A/0402Grant permission30 Aug 2023368 mThe development will consist of extensions to the existing 'Site Services' and 'Goods In' dock areas of the distribution centre building, internal demolition and reconfiguration works and all associated site development works.
F22A/0664Refuse permission for retention20 Jan 2023366 mRetention permission for the use of an existing depot for the storage of empty containers on a c.2,7ha site at Compass Distribution Park, Santry, Co. Dublin including associated security hut of 9.5 sqm, security fencing, 7 no. lighting columns and flood lighting and all associated site works
F22A/0610Invalid application due to site notice23 Nov 2022366 mFor Retention permission for the use of an existing depot for the storage of empty containers on a c. 2,7ha site at Compass Distribution Park, Santry, Co. Dublin, including associated security hut of 9.5 sqm, security fencing, 7 no. lighting columns and flood lighting and all associated site works.

Appeals

ACP caseTypeOutcomeDecidedDistance
314724Railway Order ApplicationOther30 Sept 20250 m
312131Private Development - ApplicationGranted with conditions9 Jul 2025136 m
315822Planning AppealRefused17 Apr 2024366 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 30 Oct 2026 New application · observations close 4 Dec 2026