PlanningRegister.ie
Observation pack · Dublin City Council

A site which previously formed part of the overall RTE Campus at Montrose, Donnybrook, Dublin 4

Cairn Homes Montrose Limited intendsto apply for Permission for a Large-Scale Residential Development (LRD) at this site, which previously formed part of the overall RTÉ Campus at Montrose, Donnybrook, Dublin 4. The site is located within the Simmonscourt Townland. The site is bounded by the Stillorgan Road (R138), 4A Stillorgan Road, ‘Belville Mews’, ‘Belville Lodge’, ‘Belville House’ to the west and south-west; RTE Campus to the south-east and east; Ailesbury Close and ‘Belville’ to the north-west; and ‘Danesfield’ and ‘Danesfield Lodge’, Seaview Terrace, ‘Ailesbury Court’, and properties along Ailesbury Road to the north and north-east. Mount Errol, a designated protected structure (RPS 7846), is located within the site. The proposed development will amend permitted Large Scale Residential Development (LRD) DCC Ref LRD 6003/22-S3 / ACP Reg. Ref.: 315488-23 (as amended by DCC Reg. Ref. WEBLRD6081/25-S3), which is currently under construction. The proposed amendments will increase the total number of residential units by 1 to 511 no. units. The revised residential mix will now comprise 8 no. studios (no change); 125 no. 1-bed apartments (no change); 328 no. 2-bed apartments (increase by 2 no.) and 50 no. 3-bed apartments (decrease by 1 no.). - Alterations to the external elevation materials, balconies/ terraces, windows, and inclusion of pergolas on Blocks 1 to 4. - Inclusion of a new entrance to Block 4. - Alteration to the unit mix of Block 1 to increase the number of units by 1 (from 20 no. to 21 no. units (20 no. 2 beds and 1 no. 3 bed). - Reduction in size of the permitted ESB Substation and switch room at ground floor of Block 1 and inclusion of a storeroom. - Inclusion of a new substation at ground level between Blocks 7 and 8. All associated works to accommodate the proposed changes, including minor internal amendments to the permitted apartments, and associated ancillary works/ landscaping including widened pedestrian entrance from the Stillorgan Road are included in this application. There is no change to the proposed building height or general scale, footprint and massing of permitted Blocks 1 – 4. The remainder of the permitted development will be delivered as permitted under DCC Ref LRD 6003/22-S3 / ACP Reg. Ref.: 315488-23 (as amended by DCC Reg. Ref. WEBLRD6081/25-S3).

Observations close 30 Oct 2026 11 days left
5 weeks from receipt (received 25 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20

The application

Reference
WEBLRD9014/26-S3a · full record
Authority
Dublin City Council
Type
Large Residential Development-3
Status
Registered Application
Applicant
Cairn Homes Montrose Limited
Units
—
Floor area
—
Site area
—
Received
25 Sept 2026
We first saw it
4 Oct 2026, 23:38
Decision due
—
Decision
not yet decided

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.No register URL is recorded for this reference; search the Dublin City Council planning register for WEBLRD9014/26-S3a.
  2. Write your observation.Quote WEBLRD9014/26-S3a at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Dublin City Council takes it online with the submission or at the counter.
  4. Submit before 30 Oct 2026.Online through the register above, or in writing to the Planning Department, Dublin City Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

  • Radon risk area × 1
    About 1 in 20 homes in this area is likely to have high radon levels
  • Recorded monument × 3
    Graveyard · Cross · R149490
  • OPW flood extent nearby floodinfo.ie
    Shown as a flag only — the OPW licence does not allow us to redistribute the extent.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
WEB3014/26Grant permission7 Oct 2026—0 mCHANGE OF USE: We, Donnybrook Fair Limited, intend to apply for permission for development at 87-91 Morehampton Road, Donnybrook, Dublin 4, D04 K6F2. The proposed development will consist of the change of use of the existing first-floor restaurant/cookery school accommodation to office use, together with the refurbishment reconfiguration of the existing office accommodation at first and second-floor levels to provide a modern office accommodation. First-floor works will include the refurbishment of the existing office accommodation, retention of the existing test kitchen and restaurant facilities for ancillary staff use, provision of a tasting room, breakout area, lobby, communications room and upgraded accessible WC/shower facilities. Second-floor works will comprise the refurbishment and reconfiguration of the existing office accommodation to provide offices, meeting rooms, support spaces, flexible working areas and upgraded accessible WC/shower facilities. Across both floors, works include associated internal alterations, building services upgrades, secure staff bicycle parking within the existing rear service yard and all associated ancillary works. The proposed development is predominantly internal in nature.
WEB3424/26Application declared invalid5 Oct 2026—0 mPROTECTED STRUCTURE: We, Muckross Park Developments Limited, intend to apply for permission for development on a site of approx. 1.19ha at Muckross Park House, Marlborough Road, Donnybrook, Dublin 4. The original Muckross Park House, including the modern chapel perimeter walls, gates and railings, and surviving part of walled garden are included in the Record of Protected Structures (RPS No. 4967). The proposed development includes works to the Protected Structure and will consist of: a) Works to the existing three-storey and part four-storey Muckross Park House and the adjoining four-storey North and South Wings, including the demolition and removal of the existing non-original top floor at Level 3 across Muckross Park House and the adjoining Wings (440 sq.m); the demolition and removal of non-original elements between Muckross Park House and the Wings comprising 71 sq.m at Level 0, 71 sq.m at Level 1 and 71 sq.m at Level 2 (213 sq.m in total); the refurbishment and conversion of the retained three-storey Muckross Park House to provide 5 no. apartments and the construction of a new setback top floor to provide 2 no. apartments; the retention, partial demolition, refurbishment, extension and conversion of the North and South Wings, including the construction of replacement setback top floors, to provide 7 no. apartments within the North Wing and 11 no. apartments within the South Wing; and associated internal alterations and works; b) Works to the existing Chapel comprising its retention, refurbishment and conversion to provide 5 no. apartments at ground-floor level and 5 no. two-storey duplex apartments above, through the insertion of three internal storeys within the existing Chapel envelope with no increase in the existing building height; the demolition and removal of the existing two-storey links and additions connecting the Chapel to Muckross Park House and the South Wing, comprising 190.5 sq.m at Level 0 and 139.5 sq.m at Level 1 (330 sq.m in total); the formation of new openings involving the localised removal of sections of the existing Chapel perimeter walls; the removal of the existing internal balcony at the north-western end of the Chapel; and associated internal alterations and works; c) The construction of a new five-storey apartment building to the rear (north-east) of the site, connected to the retained North Wing, to provide 29 no. apartments; d) The construction of 6 no. two-storey terraced dwellings within the remaining part of the walled garden; e) The proposed development provides for the demolition of approximately 983 sq.m of existing floor area in total and the provision of 70 no. residential units, comprising 2 no. studio units, 19 no. one-bedroom units, 38 no. two-bedroom units and 11 no. three-bedroom units; f) The provision of 44 no. surface car parking spaces, inclusive of 3 no. accessible spaces; g) The provision of 135 no. resident bicycle parking spaces and 36 no. visitor bicycle parking spaces; h) The provision of approximately 2,837 sq.m of public open space, including the retention and enhancement of the existing front parkland and mature trees, new tree and other planting, meadow areas, landscaped amenity areas, pedestrian connections to Marlborough Road, seating and a natural play area; i) The provision of approximately 1,213 sq.m of communal open space, comprising a landscaped central courtyard, a smaller landscaped courtyard and the retained historic walled garden, including the retention and repair of the historic stone garden wall and the provision of an orchard meadow, new tree, hedge and other planting and seating areas; j) Alterations to the existing vehicular, pedestrian and cyclist access arrangements from Marlborough Road, including the removal of 4 no. existing non-original entrance piers, the construction of 2 no. new entrance piers, the restoration of the protected gates and railings, renewal of the tree-lined entrance drive, and associated internal circulation arrangements; and k) All associated and ancillary site development works, including hard and soft landscaping, tree and hedge planting, biodiversity and SuDS planting, boundary treatments, public lighting, drainage and SuDS infrastructure, plant, an ESB substation, services and all associated site development works.
WEB2970/26Grant retention permission2 Oct 2026—0 mRETENTION: The development consists of the provision of a plant area (c. 25 sq.m) to the rear of the building and all associated site development works.
WEB5434/25Grant permission1 Oct 2026—0 mPROTECTED STRUCTURE: Pembroke Partnership Limited intends to apply for permission for development on a site of c.0.25 hectares at the former Donnybrook Laundry at The Crescent, Donnybrook, Dublin 4 (A Protected Structure is located within the site: a chimney stack (RPS Ref. 8713)). The development will consist of the demolition of existing structures at the site (c. 1,166 sq m). The chimney stack and the former two storey laundry building in south-eastern corner of site are to be retained. The development will also consist of a new residential development of 38 no. units, comprising: - the refurbishment of the existing laundry building to provide 4 no. units (2 no. two bed duplex units and 2 no. three bed houses); - the construction of 3 no. new blocks ranging in height from 3-6 storeys to provide 34 no. units comprising: o 31 no. apartments (1 no. studio unit, 17 no. one bed units, 7 no. two bed units; and 6 no. three bed units); and o 3 no. three bed houses. The refurbishment works to the former laundry building will include provision of openings within the eastern, southern and western elevations to provide new windows and access points; and provision of new openings to the existing roof. The proposed development will also consist of private, communal and public open space, surface car parking, bicycle parking, motorcycle parking, EV charging, waste storage facilities, vehicular and pedestrian access / egress and associated circulation routes, including the widening and improvement of the existing vehicular entrance to the property from The Crescent, hard and soft landscaping, boundary treatment, SUDs measures and all other associated site development works above and below ground. The planning application may be inspected or purchased at a fee not exceeding the reasonable cost of making a copy, at the offices of Dublin City Council, Planning Department, Block 4, Ground Floor, Civic Offices, Wood Quay, Dublin 8 during its public opening hours (9.00a.m.- 4.30p.m.). A submission or observation in relation to the application may be made in writing to the planning authority on payment of the prescribed fee (€20.00) within the period of 5 weeks beginning on the date of receipt by the authority of the application, and such submissions or observations will be considered by the planning authority in making a decision on the application. The planning authority may grant permission subject to or without conditions, or may refuse to grant permission.
WEBLRD6090/26-S3Application declared invalid28 Sept 2026—0 mPROTECTED STRUCTURE: Cairn Homes Montrose Limited intend to apply for Permission for a Large-Scale Residential Development (LRD) at this site, which previously formed part of the overall RTÉ Campus at Montrose, Donnybrook, Dublin 4. The site is located within the Simmonscourt Townland. The site is bounded to the north, west and south by existing construction of blocks 1-4 and 6-10. To the east/ south east is the remaining RTE Campus. The RTE Campus includes buildings in the Record of Protected Structures (RPS 8888). Mount Errol, a protected structure (RPS 7846), is located north west of the site. The proposed development is for a single apartment block (Block 5), ranging in height from 8 to 13 storeys (with additional roof level plant area above). The proposed building will provide 117 residential units (in the form of 58 no. 1 beds, 57 no. 2 beds and 2 no. 3 beds) and a licensed cafe/ restaurant at ground floor level. The roof level will provide plant, solar PV panels, and telecommunications infrastructure with associated ancillary equipment and cabinets. Minor amendments are also proposed to permitted development ACP Reg. Ref.: 315488-23 (as amended by DCC Reg. Ref. WEBLRD6081/25-S3) to provide additional car and cycle parking, landscaping along with all associated works to accommodate these changes. The remainder of the permitted development will be delivered as permitted under ACP Reg. Ref.: 315488-23(DCC Ref LRD 6003/22-S3) and as subsequently amended by DCC Reg. Refs. WEBLRD6081/25-S3 and WEBLRD6092/25-S3. All application documentation and information is available to view online at the following website set up by the applicant: www.montroseblock5lrd.com
WEBLRD9014/26-S3Application declared invalid23 Sept 2026—0 mProtected Structure: Cairn Homes Properties Limited intends to apply for Permission for a Large-Scale Residential Development (LRD) at this site, which previously formed part of the overall RTÉ Campus at Montrose, Donnybrook, Dublin 4. The site is located within the Simmonscourt Townland. The site is bounded by the Stillorgan Road (R138), 4A Stillorgan Road, ‘Belville Mews’, ‘Belville Lodge’, ‘Belville House’ to the west and south-west; RTE Campus to the south-east and east; Ailesbury Close and ‘Belville’ to the north-west; and ‘Danesfield’ and ‘Danesfield Lodge’, Seaview Terrace, ‘Ailesbury Court’, and properties along Ailesbury Road to the north and north-east. Mount Errol, a designated protected structure (RPS 7846), is located within the site. The proposed development will amend permitted Large Scale Residential Development (LRD) DCC Ref LRD 6003/22-S3 / ACP Reg. Ref.: 315488-23 (as amended by DCC Reg. Ref. WEBLRD6081/25-S3), which is currently under construction. The proposed amendments will increase the total number of residential units by 1 to 511 no. units The revised residential mix will now comprise 8 no. studios (no change); 125 no. 1-bed apartments(no change); 328 no. 2-bed apartments(increase by 2 no.) and 50 no. 3-bed apartments (decrease by 1 no.). Alterations will include: Alterations to the external elevation materials, balconies/ terraces, windows, and inclusion of pergolas on Blocks 1 to 4. Inclusion of a new entrance to Block 4. Alteration to the unit mix of Block 1 to increase the number of units by 1 (from 20 no. to 21 no. units l ( 20 no. 2 beds and 1 no. 3 bed)). Reduction in size of the permitted ESB Substation and switch room at ground floor of Block 1 and inclusion of a storeroom. Inclusion of a new substation at ground level between Blocks 7 and 8. All associated works to accommodate the proposed changes, including minor internal amendments to the permitted apartments, and associated ancillary works/ landscaping including widened pedestrian entrance from the Stillorgan Road are included in this application. There is no change to the proposed building height or general scale, footprint and massing of permitted Blocks 1 – 4. The remainder of the permitted development, Blocks 6-10, site services, and all other works will be delivered as permitted under DCC Ref LRD 6003/22-S3 / ACP Reg. Ref.: 315488-23 (as amended by DCC Reg. Ref. WEBLRD6081/25-S3). All application documentation and information is available to view online at the following website set up by the applicant: www.montroseamendmentlrd.com The Planning Application may be inspected or purchased at a fee not exceeding the reasonable cost of making a copy, at the offices of Dublin City Council, Planning Department, Block 4, Ground Floor, Civic Offices, Wood Quay, Dublin 8 during its public opening hours (9.00a.m.-4.30p.m.) or on Dublin City Council Website: www.dublincity.ie. A submission or observation in relation to the application may be made in writing to the planning authority on payment of the prescribed fee (€20.00) within the period of 5 weeks beginning on the date of receipt by the authority of the application, and such submissions or observations will be considered by the planning authority in making a decision on the application. The planning authority may grant permission subject to or without conditions, or may refuse to grant permission.
WEB3051/26Application declared invalid21 Aug 2026—0 mNOT IN DCC FUNCTIONAL AREA: Retention permission for hip to gable non habitable attic conversion; single storey extension to rear garden; garage conversion; and widened driveway.
WEB3020/26Application declared invalid18 Aug 2026—0 mThe development will consist of part single storey rear extension plus part two storey rear extension plus conversion of attic with dormer roof to rear roof slope and internal alterations and all associated site works.

Appeals

ACP caseTypeOutcomeDecidedDistance
324275Appeal - LRDGranted with conditions28 Aug 2026427 m
501123Planning AppealRefused21 Jul 2026377 m
500647Planning AppealGranted with conditions8 Apr 2026422 m
500141Planning AppealGranted25 Feb 2026455 m
500005Planning AppealGranted with conditions20 Feb 2026471 m
500177Planning AppealGranted18 Feb 2026100 m
323768Planning AppealGranted with conditions9 Feb 2026411 m
323605Planning AppealGranted with conditions9 Dec 2025449 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 25 Sept 2026 New application · observations close 30 Oct 2026

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 4 Oct 2026, 23:38. Not legal advice — confirm the deadline with Dublin City Council before relying on it.