Planning permission sought for a)construction of single storey rear extension w

Observations close 16 Oct 2026 5 days left
5 weeks from receipt (received 11 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 5 Nov 2026

The application

Reference
D26B/0497/WEB · full record
Authority
Dún Laoghaire-Rathdown County Council
Type
Permission
Status
Referral
Applicant
not published by the national dataset — see the council register
Units
—
Floor area
—
Site area
338 m²
Received
11 Sept 2026
We first saw it
22 Sept 2026, 16:10
Decision due
5 Nov 2026
Decision
not yet decided

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://planning.agileapplications.ie/dunlaoghaire/application-details/?ref=D26B/0497/WEB.
  2. Write your observation.Quote D26B/0497/WEB at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Dún Laoghaire-Rathdown County Council takes it online with the submission or at the counter.
  4. Submit before 16 Oct 2026.Online through the register above, or in writing to the Planning Department, Dún Laoghaire-Rathdown County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
R2
Existing residential
Objective A: A To provide residential development and improve residential amenity while protecting the existing residential amenitiesDR-001:DP:county-development-plan-2022-20281 Apr 2022 → 1 Apr 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: DLR DR-001:DP:county-development-plan-2022-2028 · fetched 11 Sept 2026, 15:17
SourceLicenceFetchedLink
DLR DR-001:DP:county-development-plan-2022-2028—11 Sept 2026, 15:17open

Designations on or near the site

  • Radon risk area × 5
    About 1 in 10 homes in this area is likely to have high radon levels · About 1 in 20 homes in this area is likely to have high radon levels · About 1 in 5 homes in this area is likely to have high radon levels

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
D26A/0449/WEBGrant permission29 Jul 2026—461 ma) Change of use of the entire premises from light industrial with offices, to
D26B/0329/WEBGrant permission22 Jul 2026—374 mA single storey flat roof porch and garage extension and all ancillary site work
D26A/0094/WEBGrant permission29 Jun 2026—242 mThe proposed development comprises of the construction of 2 no. four bedroom dwe
REF7126S5 dec exempt9 Jun 2026—282 mThe installing of 100 mm wrap around insulation with a smooth finish to the outs
REF6926S5 dec exempt5 Jun 2026—492 mOut door wall insulation.
D26B/0315/WEBDeclare application invalid29 May 2026—380 mThe development will consist of a single storey flat roof porch and garage exte
D25A/0879/WEBGrant permission27 May 2026—160 mConstruction of a single-storey extension to the side, fore and rear of the exis
D26A/0099/WEBGrant permission25 May 2026—246 ma) Demolition of existing single storey detached garage and steel shed, b) Const

Appeals

ACP caseTypeOutcomeDecidedDistance
501759Planning Appealopen23 Jul 2026242 m
501578Planning Appealopen18 Jun 2026246 m
501522Planning Appealpending10 Jun 2026139 m
322889Building Control - Fire Safety CertificateGranted with conditions9 Feb 2026461 m
500661Planning AppealInvalid9 Jan 2026242 m
323310Final Map AppealSplit6 Nov 2025313 m
322623Planning AppealGranted with conditions24 Sept 2025280 m
322654Planning AppealGranted with conditions24 Sept 2025280 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 11 Sept 2026 New application · observations close 16 Oct 2026