PlanningRegister.ie
Observation pack · Donegal County Council

FIGARY , FAHAN , LIFFORD PO

CONSTRUCTION OF A SINGLE STOREY DWELLING WITH DOMESTIC GARAGE, CONNECTION TO ON-SITE WASTEWATER TREATMENT SYSTEM & ASSOCIATED SITE WORKS

Observations close 29 Oct 2026 15 days left
5 weeks from receipt (received 24 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 18 Nov 2026

The application

Reference
2661770 · full record
Authority
Donegal County Council
Type
PERMISSION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
1
Floor area
117 m²
Site area
7,812 m²
Received
24 Sept 2026
We first saw it
29 Sept 2026, 23:03
Decision due
18 Nov 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/DonegalCC/AppFileRefDetails/2661770/0.
  2. Write your observation.Quote 2661770 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Donegal County Council takes it online with the submission or at the counter.
  4. Submit before 29 Oct 2026.Online through the register above, or in writing to the Planning Department, Donegal County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

  • NIAH-recorded building × 1
    Ennerdale

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2661546Conditional1 Oct 20261435 mDWELLING AS CONSTRUCTED, WHICH DIFFERS FROM THE DWELLING PREVIOUSLY GRANTED PLANNING PERMISSION (PLANNING REF. NO. 15,881A REFERS), ALONG WITH ALL ASSOCIATED SITE WORKS AND CONNECTION TO SERVICES
2661453Conditional17 Sept 20260409 m(1) CONSTRUCTION OF A FIRST FLOOR EXTENSION AND GROUND FLOOR SIDE EXTENSION, (2) RELOCATION OF FRONT PORCH, AND (3) ALL ASSOCIATED SITE WORKS
2562240Conditional6 Aug 20261215 mDEMOLITION OF EXISTING DWELLING AND CONSTRUCTION OF A REPLACEMENT DWELLING WITH CONNECTION TO MAIN SEWER, DOMESTIC GARAGE AND ALL ASSOCIATED SITE DEVELOPMENT WORKS. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
2660843Refused2 Jul 20262299 mCONSTRUCTION OF 2 SMALL DWELLINGS WITH CONNECTION TO MAIN SEWER VIA A HOLDING TANK AND PUMP SYSTEM, ALONG WITH ALL ASSOCIATED SITE WORKS
2650039Refused30 Apr 20261319 m(A) CONSTRUCTION OF DWELLING HOUSE WITH CONNECTION TO PRIMARY WASTEWATER TREATMENT PLANT ALONG WITH CONNECTION TO EXISTING PUBLIC SEWER AND (B) CONSTRUCTION OF A DOMESTIC GARAGE WITH ALL ASSOCIATED SITE WORKS
2562135Conditional20 Mar 20260124 mCONSTRUCTION OF TWO HOUSES, WITH EACH DWELLING HAVING A SEPARATE VEHICULAR ACCESS AND CONNECTION TO EXISTING SERVICES INCLUDING WASTEWATER TREATMENT SYSTEM WITH DISCHARGE TO PUBLIC SEWER
2562206Conditional12 Feb 2026064 mA TEN-YEAR PLANNING PERMISSION FOR DEVELOPMENT AT THE EXISTING BUNCRANA WASTEWATER TREATMENT PLANT (WWTP) LOCATED AT RAILWAY ROAD, BALLYMACARRY LOWER, CO. DONEGAL; THE EXISTING FAHAN WWTP LOCATED AT CARRONTLIEVE, FAHAN, CO. DONEGAL; AND ALONG THE R238 REGIONAL ROAD WITHIN THE TOWNLANDS OF CARRONTLIEVE, CARROWMULLIN, FIGARY, LISFANNAN, LUDDAN, AND BALLYMACARRY LOWER. THE PROPOSED DEVELOPMENT WILL CONSIST OF: (1) UPGRADE WORKS TO THE EXISTING BUNCRANA WWTP REQUIRING AN EXPANSION OF THE EXISTING SITE TO INCREASE ITS DESIGN POPULATION EQUIVALENT (PE) FROM 13,200PE TO 17,700PE COMPRISING (A) CONSTRUCTION OF A SECONDARY TREATMENT TANK, BLOWERS AND SOUND ATTENUATION BARRIER, PUMP SUMP AND VENT STACK, FLOW METER CHAMBER, VALVE CHAMBER, ADMINISTRATION BUILDING, FLOOD PROTECTION WALL, 2 NO. PICKET FENCE THICKENER TANKS, A SITE DRAINAGE PUMPING STATION, INTERNAL SITE ACCESS ROAD, INTERCONNECTING PIPEWORK AND MANHOLES AND 4 NO. PARKING SPACES, (B) INTERNAL UPGRADES TO THE INLET WORKS BUILDING, INTERNAL UPGRADES TO THE CONTROL AND SLUDGE DEWATERING BUILDING, INTERNAL UPGRADES TO THE OUTFALL PUMPING STATION, REPURPOSING OF THE PRIMARY SETTLEMENT TANKS AS FINAL EFFLUENT BALANCING TANKS, RECONFIGURATION OF THE FLOW DISTRIBUTION CHAMBER AND INTERNAL UPGRADES TO THE SLUDGE HOLDING TANK, (C) REPLACEMENT OF THE EXISTING SITE ACCESS GATE WITH A PALISADE SECURITY GATE, (D) INSTALLATION OF ROOF MOUNTED SOLAR PHOTOVOLTAIC (PV) PANELS ON SOUTH FACING ROOFS OF THE EXISTING INLET WORKS, CONTROL AND SLUDGE DEWATERING AND PROPOSED ADMINISTRATION BUILDINGS, (E) DECOMMISSIONING AND DEMOLITION OF THE EXISTING SITE DRAINAGE PUMPING STATION, GAS HOLDING TANK, PICKET FENCE THICKENER AND SLUDGE DIGESTION TANK AND (F) ALL HARD AND SOFT LANDSCAPING WORKS INCLUDING SCREEN PLANTING AND ALL ASSOCIATED ANCILLARY WORKS INCLUDING SITE WORKS AND TEMPORARY WORKING AREAS, (2) UPGRADE WORKS TO THE EXISTING FAHAN WWTP TO CONVERT IT INTO A WASTEWATER PUMPING STATION (WWPS) COMPRISING (A) CONSTRUCTION OF A STORMWATER HOLDING TANK, PUMP SUMP AND VENT STACK, VALVE CHAMBER, INLET FLUME, SURGE VESSEL, WET KIOSK, 2 NO. CONTROL KIOSKS, CHEMICAL SKID, BUNDED CHEMICAL STORAGE TANK, EMERGENCY SHOWER, WELFARE UNIT, FLOOD PROTECTION WALL WITH GATE, INTERCONNECTING PIPEWORK AND MANHOLES, (B) DECOMMISSIONING AND DEMOLITION OF THE SITE GATE AND WING WALLS, SEPTIC TANK AND PRELIMINARY EQUIPMENT, (C) MATERIAL ALTERATION OF THE EXISTING SITE ACCESS TO INCORPORATE A NEW AND REALIGNED SECURITY MESH SITE GATE AND WINGWALLS AN
2561608Conditional7 Nov 2025158 mCONSTRUCTION OF A DWELLING WITH CONNECTION OF PRIMARY TREATMENT PLANT ALONG WITH CONNECTION TO EXISTING SERVIES, DOMESTIC GARAGE AND ALL ASSOCIATED SITE DEVELOPMENT WORKS

Appeals

ACP caseTypeOutcomeDecidedDistance
501404—open25 May 2026319 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 24 Sept 2026 New application · observations close 29 Oct 2026
  • 24 Sept 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 29 Sept 2026, 23:03. Not legal advice — confirm the deadline with Donegal County Council before relying on it.