PlanningRegister.ie
Observation pack · Donegal County Council

AGHANGADDY GLEBE , RAMELTON , LETTERKENNY PO

(1) CONSTRUCTION OF A SINGLE STOREY FARM SHOP BUILDING TO INCLUDE COFFEE / ARTISAN PRODUCE SALES, INCORPORATING INDOOR AND OUTDOOR SEATING, ANCILLARY TOILETS, KITCHEN AND STORAGE / PLANT AREAS AND (2) PROVISION OF A SEWAGE TREATMENT SYSTEM AND ALL ASSOCIATED CAR PARKING / SITE WORKS

Observations close 8 Dec 2026 14 days left
5 weeks from receipt (received 3 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 6 Jan 2027

The application

Reference
2662018 · full record
Authority
Donegal County Council
Type
PERMISSION
Status
NEW APPLICATION
Site area
2,610 m²
Received
3 Nov 2026
Decision due
6 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/DonegalCC/AppFileRefDetails/2662018/0.
  2. Write your observation.Quote 2662018 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Donegal County Council takes it online with the submission or at the counter.
  4. Submit before 8 Dec 2026.Online through the register above, or in writing to the Planning Department, Donegal County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2660886Conditional9 Jul 2026440 mCONSTRUCTION OF A SINGLE STOREY DWELLING AND SINGLE STOREY GARAGE, INSTALLATION OF A SEWAGE TREATMENT SYSTEM AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
2660482Conditional8 May 20265 mCONSTRUCTION OF A SLATTED CATTLE / CUBICLE SHED WITH INTEGRATED UNDERGROUND SLURRY STORAGE TANKS AND ALL ASSOCIATED SITE WORKS WITHIN THE EXISTING FARMYARD COMPLEX
2460576Conditional6 Jun 20241485 mERECTION OF A DWELLING HOUSE WITH SEPTIC TANK AND DOMESTIC GARAGE INCLUDING ALL OTHER SITE DEVELOPMENT WORKS
2350250Refused20 Apr 20231496 mERECTION OF A DWELLING HOUSE AND WASTE WATER TREATMENT SYSTEM INCLUDING ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS
2350251Refused20 Apr 20231486 mERECTION OF A DWELLING HOUSE AND WASTE WATER TREATMENT SYSTEM INCLUDING ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS
2251053Conditional4 Aug 2022436 mCONSTRUCTION OF A DOMESTIC GARAGE
2250246Conditional7 Apr 2022290 mRETENTION AND COMPLETION OF EXTENSION TO THE REAR OF EXISTING DWELLING HOUSE CURRENTLY UNDER CONSTRUCTION

What has happened on this file

  • 3 Nov 2026 New application · observations close 8 Dec 2026
  • 3 Nov 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 11 Nov 2026, 23:00. Not legal advice — confirm the deadline with Donegal County Council before relying on it.