PlanningRegister.ie
Observation pack · Donegal County Council

DRUMKEELAN , MOUNTCHARLES , DONEGAL PO

DEVELOPMENT AT EXISTING OFFICES, WORKSHOP AND STORAGE YARD CONSISTING OF (1) RETENTION OF PITCHED ROOF 2-BAY PORTAL FRAME METAL CLAD EXTENSION TO THE SOUTH-WEST ELEVATION OF PREVIOUSLY APPROVED BUILDING AT THE REAR OF THE SITE TO MATCH THE EAVES AND RIDGE HEIGHT OF THE EXISTING AND (2) CHANGE OF USE FROM STORAGE TO MANUFACTURING OF POLES IN THE PORTAL FRAME BUILDING AT THE REAR OF THE SITE AND ALL ASSOCIATED SITE DEVELOPMENT WORKS

Observations close 23 Dec 2026 28 days left
5 weeks from receipt (received 18 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 21 Jan 2027

The application

Reference
2662135 · full record
Authority
Donegal County Council
Type
PERMISSION
Status
PRE_VALIDATION
Site area
1.71 ha
Received
18 Nov 2026
Decision due
21 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/DonegalCC/AppFileRefDetails/2662135/0.
  2. Write your observation.Quote 2662135 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Donegal County Council takes it online with the submission or at the counter.
  4. Submit before 23 Dec 2026.Online through the register above, or in writing to the Planning Department, Donegal County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedDistanceDescription
2562309Conditional30 Apr 20260 m(1) CONSTRUCTION OF A TWO-STOREY RESEARCH AND DEVELOPMENT AND OFFICE FACILITY BUILDING WITH INTERCONNECTION TO THE EXISTING WORKSHOP AND OFFICES, (2) CONSTRUCTION OF A SINGLE STOREY PITCH ROOF EXTENSION TO THE EXISTING WORKSHOP TO MATCH THE EAVES AND RIDGE HEIGHT OF THE EXISTING, (3) RELOCATION AND UPGRADING OF THE VEHICULAR ENTRANCE AND ALTERATIONS TO THE EXISTING ENTRANCE AND (4) INSTALLATION OF A NEW SEPTIC TANK / SEWERAGE TREATMENT SYSTEM AND PERCOLATION AREA AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
2660446Conditional30 Apr 2026436 mCONSTRUCTION OF A NEW 144M² EXTENSION TO AN EXISTING AGRICULTURAL SHED, INCORPORATING A SLATTED UNDERGROUND TANK, A SHEEP HANDLING FACILITY, AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
2560824Conditional5 Dec 2025473 mQUARRIED AREA COMPRISING 2.801HA OUTSIDE THE SITE HISTORIC QUARRY AREA AND PERMISSION FOR (1) CONTINUATION AND EXTENSION OF THE QUARRY AREA TO A TOTAL OF 2.141HA INCLUDING (A) USE AND UPGRADING OF EXISTING QUARRY ENTRANCES, (B) RELATED STRUCTURES AND DEVELOPMENTS AND (C) DRAINAGE AND SETTLEMENT PONDS AND (2) PROPOSED (A) LANDSCAPING BERM AND PLANTING/GRASS STRIPS, (B) CONCRETE APRON AND DRAINAGE GRID AT THE ENTRANCE, REFUELING PAD WITH HYDROCARBON INTERCEPTOR AND (C) ALL ANCILLARY DEVELOPMENT AND ASSOCIATED SITE WORKS. A 25-YEAR PLANNING PERMISSION IS BEING SOUGHT FOR THIS QUARRY
2460866Conditional28 Nov 20240 m(1) EXISTING SHED AS A COMMERCIAL UNIT, (2) EXCAVATED SITE AND HARD STANDING AREAS AND PERMISSION FOR (1) ERECTION OF AN EXTENSION TO THE EXISTING SHED, (2) INSTALLATION OF A NEW SEWERAGE TREATMENT SYSTEM AND ALL ASSOCIATED SITE DEVELOPMENT WORKS

What has happened on this file

  • 18 Nov 2026 New application · observations close 23 Dec 2026
  • 18 Nov 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 24 Nov 2026, 23:00. Not legal advice — confirm the deadline with Donegal County Council before relying on it.