PlanningRegister.ie
Observation pack · Galway County Council

Fairyhill , Lios na Si , Portumna

and completion of 2 No. 3-bedroom semi detached dwellings in Block 1 as granted under original planning permission 05/2868 and construction of a residential development with a total of 7 terraced dwellings (4 No. 3-bedroom and 3 No. 2-bedroom units). The provision of a site entrance off the existing Lios na Si housing estate, internal road, paving, pathways, parking, amenity space, streetlighting, connection to existing public services (foul water & mains water supply) an attenuation tank and all associated site development works, boundary treatments, landscaping and ancillary services to complete the development. A Natura Impact Statement (NIS) will be submitted to the planning authority with this application

Observations close 19 Oct 2026 window closed
5 weeks from receipt (received 14 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 8 Nov 2026

The five-week window has passed. Late observations are returned unread. If the council has decided, the next door is the appeal window — but under s.37 only the applicant and those who made a valid observation may appeal.

The application

Reference
26233 · full record
Authority
Galway County Council
Type
RETENTION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
2
Floor area
824 m²
Site area
4,098 m²
Received
14 Sept 2026
We first saw it
22 Sept 2026, 16:10
Decision due
8 Nov 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/GalwayCC/AppFileRefDetails/26233/0.
  2. Write your observation.Quote 26233 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Galway County Council takes it online with the submission or at the counter.
  4. Submit before 19 Oct 2026.Online through the register above, or in writing to the Planning Department, Galway County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
G1
Open space with recreation
Open Space/Recreation & Amenity: To protect and enhance existing open space and provide for recreational and amenity space.galway county development plan 2022 202820 Jun 2022 → 19 Jun 2028
R2
Existing residential
Residential Existing: To protect and improve residential amenities of existing residential areasgalway county development plan 2022 202820 Jun 2022 → 19 Jun 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: Galway County Council development plan zoning · fetched 27 Sept 2026, 19:37
SourceLicenceFetchedLink
Galway County Council development plan zoning—27 Sept 2026, 19:37open

Designations on or near the site

Nothing designated within 100 m of the site.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2699Conditional3 Sept 20260319 mfor construction of an extension to the side (East) and rear (North) elevations of an existing detached dormer dwelling; demolition of a single storey annex to the side (East) elevation of the existing dwelling with minor elevational alterations to the dwelling; demolition of an existing domestic store to the side of the existing dwelling and construction of a new domestic store in lieu of the demolished building; widening of the existing vehicular access and all associated site works
2660087Conditional19 Mar 20260353 mfor the construction of a new storage/warehouse facility along with ancillary site works as well as retention permission to existing trade shop entrance
25250Unconditional14 Nov 20250324 mof planning ref. 19/1287 for developments at; Connaught Harbour to Portumna Bridge, Fairyhill following the ESB flood embankment, through Lough Derg Water Recreation Park, Portumna to Portumna Forest Park, Portumna Demesne, County Galway. The development consists of two Phases, Phase 1: a new multi-use shared leisure route (Blueway), 2.4km in length, with tailored surface finishes, information, directional and safety signage and all other associated ancillary works. The route commences at Portumna Bridge, crosses over the ESB flood bank via a new timber boardwalk, following along the toe of the flood bank connect to Lough Derg Water Recreation Park. A new cycle advisory lane, marked parking bays upgrade to footpaths shall be constructed at Lough Derg Water Recreation. The route continues through adjacent farm land which connects to OPW lands that lead to the existing access road at Portumna Forest Park. Phase 2: a new 8 berth marina, incorporating boat pump-out at Connaught Harbour, the removal of the two existing buildings and construction of a new car parking area. Located at the existing Waterways Ireland works yard at Portumna bridge the three existing building shall be removed, for the construction of a new car parking and amenity area, including a new timber covered space incorporating a bat roost. Existing footpaths shall be repaired where required and a new Toucan road crossing shall be constructed to connect to the Blueway constructed in Phase 1. The proposal will involve works to or within the curtilage of the following protected structures; Portumna Harbour, Fairyhill (RPS 477) and Portumna Castle, Portumna Demesne (PRS 3785). A Natura Impact Statement have been prepared and included as part of the planning application
2561261Conditional30 Oct 20251253 mfor the construction of a serviced dwellinghouse, new vehicular entrance and all associated services. The proposed development is adjacent to Palmerstown House, protected structure (RPS No. 3766) as defined by Part IV of the 2000 Planning & Development Act
2461297Refused26 Sept 20250484 mfor; 1) Demolition works to existing sheds (92 sq.m) and existing boundary walls; 2) The extension and reconfiguration of the existing car park with the addition of 14 extra car parking spaces bringing the total from 84 to 98 spaces including 20 EV charging spaces, 5 disabled spaces and 6 parent and child spaces. 3) Alterations to the existing entrance/exits onto Dominick Street to include the closure of one number exit and enlargement of second number exit from 6.0m to 8.0m wide, and the addition of an entrance only access 4.5m wide from the Clonfert Avenue with pedestrian crossing. 4) Site works to include the following, construction of a 2.0m high boundary wall, kerbing, footpaths, surfacing, associated drainage and installation of traffic management line marking. Gross floor space of any demolition: 92.00 sqm
2560839Conditional19 Aug 20250244 mto construct 1) a new single storey extension to rear of existing house. 2) Minor alterations and refurbishment to existing house. 3) A domestic garage and all associated site works. Gross floor space of proposed works: 27.00 sqm(G), 74 sqm(extension)
2560537Conditional25 Jun 20250290 mto change the use of three vacant ground floor commercial units to three number apartments, and to change the use of an adjacent vacant shell core unit, to nine number apartments. Permission is also sought for elevational changes to both blocks, along with changes to the site, to allow for a change in car parking layout, amenity space, and boundary treatments. Gross floor space of proposed works: 1,186 sqm
24279Conditional20 Mar 2025193 mfor: (a) the construction of a two storey extension to the rear of an existing single storey dwelling. (b) Demolition of a single storey annex to the rear of the existing dwelling with alteration of the existing roof form from hipped roof to gable roof which shall include for the conversion of the existing attic space to habitable accommodation. Alterations to the existing dwelling shall include for modifications to the internal layout arrangement, minor changes to the exterior, removal of two chimneys and the application of external wall insulation and render to the existing elevations. (c) Demolition of an existing domestic store to the rear of the existing dwelling and construction of a new domestic store in lieu of the demolished building. (d) Provisions for an additional on site car parking space and (e) all associated site works. Gross floor space of proposed works: 199.03 (extension), 6.24 sqm (garage/store). Gross floor space of any demolition: 51.14 sqm

Appeals

ACP caseTypeOutcomeDecidedDistance
500130—Granted with conditions19 May 2026484 m
323042—open15 Jul 2025290 m
315409—Granted with conditions9 Apr 2025317 m
320613—Granted with conditions11 Feb 2025176 m
316699—Split23 Aug 2023219 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 14 Sept 2026 New application · observations close 19 Oct 2026
  • 14 Sept 2026 Decision