PlanningRegister.ie
Observation pack · Galway County Council

Cill Chiaráin , Scoil Naomh Ciarán Conamara , County Galway

Chun cóiríocht fheabhsaithe agus bhreise a sholáthar dodhaltaí agus don fhoireann atá ann cheana féin. Áireofar sna hoibreachta atá beartaithe, seomra ranga a fheidhmeoidh mar spás ciún/spás sábhailte, seomra do ghniomhaíochtaí éagsúla, áiseanna leithris/cithfholcadáin inrochtana do dhaoine a dteastaíonn cúnamh uathu, spás stórála, oifig a bhfuil achar urláir comhlán 207 méadar cearnach aici, chomh maith le scioból 16 meadar cearnach a choinneáil

Observations close 27 Nov 2026 1 day left
5 weeks from receipt (received 23 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 17 Dec 2026

The application

Reference
2661754 · full record
Authority
Galway County Council
Type
PERMISSION
Status
NEW APPLICATION
Site area
2,161 m²
Received
23 Oct 2026
Decision due
17 Dec 2026

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/GalwayCC/AppFileRefDetails/2661754/0.
  2. Write your observation.Quote 2661754 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Galway County Council takes it online with the submission or at the counter.
  4. Submit before 27 Nov 2026.Online through the register above, or in writing to the Planning Department, Galway County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Designations on or near the site within 100 m

  • NIAH-recorded building × 1
    Cill Chiaráin [Saint Ciaran's Catholic Church]

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2360506Conditional5 Jun 2024155 mof the provision of 1 No. new single pole structure and refurbishment and upgrading works [including (where necessary) replacement of existing poles along the existing overhead electricity line, minor ground works e.g. replacement or installation of stays, and maintenance or improvement works]; and all associated ancillary works including the provision of temporary accessways. Replacement poles will be constructed at, or immediately adjacent to, the existing structures that they will replace. Replacement poles and the new pole will have a maximum height of 12m above ground; and be similar in appearance to existing poles. Planning permission is sought for a 10 year period. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application
2360367Conditional7 Jul 20231364 mto construct a new side extension including all associated site works
2260861Conditional8 Feb 20231193 mto retain dwelling house and its services as constructed on revised site boundaries. Gross floor area of retained works: 157.8sqm
212274Conditional19 Apr 20221477 mto: 1) demolish an existing house and the construction of a new dwelling house, 2) construct new domestic garage, 3) replace existing septic tank and percolation area with a new effluent treatment system and polishing filter as well as all ancillary site works and site services. Gross floor space of proposed works: 178.16 sqm (house) & 40 sqm (house)
212363Conditional16 Feb 20221146 mfor: a) alterations to the existing dwelling first floor (100.11 sqm) which will include a study/bedroom & bathroom, b) alterations to the existing elevations including 3 dormers/ rooflights to the front elevation & c) a new treatment plant/percolation area and all associated site works. Gross floor space of proposed works: 100.11 sqm

Appeals

ACP caseTypeOutcomeDecidedDistance
311057Refused13 Mar 20230 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 23 Oct 2026 New application · observations close 27 Nov 2026
  • 23 Oct 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 3 Nov 2026, 23:01. Not legal advice — confirm the deadline with Galway County Council before relying on it.